The Obigarm-Nurobod road section of the existing M41 highway, which carries about 3,000 vehicles per day, will be inundated once the HPP reservoir has filled to operating levels. The realignment of this road section through the river valley is not part of the Rogun HPP project. A bypass road must be completed and opened to traffic by latest November 2023, the date by which the rising water in the HPP reservoir will have inundated several critical sections of the M41 highway. No other part of Tajikistan's national highway network can provide for this traffic, and the only alternative route would represent a deviation of about 500 km. The government has requested ADB's assistance to construct a 72 km long road section that will bypass the HPP reservoir through mountainous terrain (the project road).
Project Name | Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm-Nurobod) Road Project | ||||
Project Number | 52042-001 | ||||
Country | Tajikistan |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Grant Loan |
||||
Source of Funding / Amount |
|
||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth Regional integration |
||||
Drivers of Change | Gender Equity and Mainstreaming Knowledge solutions Partnerships |
||||
Sector / Subsector | Transport / Road transport (non-urban) |
||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||
Description | The Obigarm-Nurobod road section of the existing M41 highway, which carries about 3,000 vehicles per day, will be inundated once the HPP reservoir has filled to operating levels. The realignment of this road section through the river valley is not part of the Rogun HPP project. A bypass road must be completed and opened to traffic by latest November 2023, the date by which the rising water in the HPP reservoir will have inundated several critical sections of the M41 highway. No other part of Tajikistan's national highway network can provide for this traffic, and the only alternative route would represent a deviation of about 500 km. The government has requested ADB's assistance to construct a 72 km long road section that will bypass the HPP reservoir through mountainous terrain (the project road). It will be constructed to two-lane asphalt surfaced standard, and will include three tunnels with a total length of about 6 km, one high level bridge about 700 m long, and 13 shorter bridges with a total length of about 975 m. The construction of some parts of the project road started in 1988 (mostly earthworks) but was suspended following the abandonment of the Rogun HPP project. | ||||
Project Rationale and Linkage to Country/Regional Strategy | Timely construction of the project road is a government priority, as reflected by its inclusion in the National Development Strategy, and its consistency with the ADB country partnership strategy. The request to finance this project was renewed by the President of Tajikistan during the visit of ADB President to Tajikistan in November 2017. Tajikistan depends heavily on its road transport corridors to support investment, job creation, trade, and ultimately economic growth and poverty reduction. Despite its strategic location, the country has a gross domestic product per capita of just $819, and 32% of the population still lives below the poverty line. Almost 70% of the population lives in rural areas, in a largely mountainous territory where only 10% of the land is suitable for cultivation. The road transport sector suffers from low quality, long travel times, and poor reliability. Four Central Asia Regional Economic Cooperation (CAREC) corridors (2, 3, 5, and 6) cross parts of Tajikistan, offering the opportunity for Tajikistan to enhance its connectivity and trade competitiveness. |
||||
Impact | (i) Economic growth promoted (ii) Competitive corridors across the CAREC region established |
Project Outcome | |
---|---|
Description of Outcome | Connectivity and safety along the Obigarm -Nurobod road improved |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Project roads constructed, and road safety awareness increased MOT''s institutional capacity on asset management strengthened Women''s access to economic opportunities enhanced |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nurobod, Obigarm |
Safeguard Categories | |
---|---|
Environment | A |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | For environment impacts, the significant earthworks and tunnel works might indicate an A category, but this is to be determined during TRTA implementation. |
Involuntary Resettlement | The proposed road alignment will follow an alignment that was defined originally in the 1980s, and which is largely clear of houses and other assets. Therefore, it is anticipated that the project will be classified as category B for involuntary resettlement impacts. |
Indigenous Peoples | There are no indigenous peoples in the project area, as defined in ADB's Safeguard Policy Statement (SPS), and thus the project will be classified as category C for indigenous people's impacts. |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Extensive consultations will be undertaken with various groups, with focus on the poor, vulnerable and marginalized groups such as women, youth, the elderly and people with disabilities. The project will create mechanisms, through which grievances and concerns will be channeled, and information dissemination and disclosure will be ensured, to empower these groups and all affected people to act as watchdogs for the proper implementation of the project. |
During Project Implementation | Consultations will be undertaken throughout project implementation period to ensure that stakeholders views are taken into consideration. |
Business Opportunities | |
---|---|
Consulting Services | Consulting services will be required for construction supervision (CS-01) and project management (CS-02). Consultants will be recruited through firms in accordance with ADB's Guidelines on the Use of Consultants (2013, as amended from time to time). Advance contracting and retroactive financing will be sought to ensure the readiness of the project. The recruitment of two consulting services are ongoing. CS-01 and CS-02 were advertised on 13 September 2019 with EOI submission deadline of 22 October 2019. |
Procurement | Procurement of all contracts through open competitive bidding will be done in accordance with ADB Procurement Policy and Regulations (2017, as amended from time to time). Advance contracting will be considered and used to expedite the Project implementation. ADB approval of advance contracting will not commit ADB to subsequently approve the project or to finance the procurement costs. Procurement for the civil works package (construction of the Obigarm-Tagikamar highway) is ongoing. The invitation for bids was posted on 19 August 2019 with bids submission deadline of 11 November 2019. |
Responsible ADB Officer | Idei, Rika |
Responsible ADB Department | Central and West Asia Department |
Responsible ADB Division | Transport and Communications Division, CWRD |
Executing Agencies |
Ministry of Transport [email protected] 14, Aini Street Dushanbe 734042 Tajikistan |
Timetable | |
---|---|
Concept Clearance | 04 Jun 2018 |
Fact Finding | 03 Jun 2019 to 11 Jun 2019 |
MRM | 10 Sep 2019 |
Approval | 05 Dec 2019 |
Last Review Mission | - |
Last PDS Update | 05 Dec 2019 |
Grant 0683-TAJ
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
05 Dec 2019 | 31 Dec 2019 | 31 Jul 2020 | 31 Dec 2024 | - | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 138.10 | Cumulative Contract Awards | |||
ADB | 110.00 | 05 Dec 2019 | 4.40 | 0.00 | 4% |
Counterpart | 28.10 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 05 Dec 2019 | 0.00 | 0.00 | 0% |
Status of Covenants | ||||||
---|---|---|---|---|---|---|
Category | Sector | Safeguards | Social | Financial | Economic | Others |
Rating | Partly satisfactory | Satisfactory | Satisfactory | - | - | - |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Title | Document Type | Document Date |
---|---|---|
Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm–Nurobod) Road Project: Obigarm–Tagikamar Road Section Land Acquisition and Resettlement Plan Implementation Compliance Report | Social Monitoring Reports | Aug 2020 |
Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm-Nurobod) Road Project: Environmental Impact Assessment | Environmental Impact Assessments | Jul 2020 |
Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm-Nurobod) Road Project: Obigarm–Tagikamar Road Section Resettlement Plan (Russian) | Resettlement Plans | Feb 2020 |
Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm–Nurobod) Road Project: Obigarm-Tagikamar Road Section Resettlement Plan | Resettlement Plans | Aug 2019 |
Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm-Nurobod) Road Project: Environmental Impact Assessment | Environmental Impact Assessments | Jul 2019 |
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
-
$110 Million Grant from ADB to Construct Obigarm-Nurobod Road in Tajikistan
ADB has approved a $110 million grant to Tajikistan to construct 30 kilometers (km) of a highway and 30 km of secondary roads between the towns of Obigarm and Nurobod in the northeast of the country.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Project Manager | Individual - Consulting | Closed | 28 Aug 2020 | 17 Sep 2020 |
Project Manager | Individual - Consulting | Closed | 28 Mar 2020 | 24 Apr 2020 |
Construction Supervision Consultant | Firm - Consulting | Closed | 13 Sep 2019 | 22 Oct 2019 |
Project Management Consultant | Firm - Consulting | Closed | 13 Sep 2019 | 22 Oct 2019 |
52042-TAJ: Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm–Nurobod) Road Project [ONRP/CW/CP-01] | Invitation for Bids | Closed | 19 Aug 2019 | 28 Oct 2019 |
52042-TAJ: CAREC Corridors 2, 3, and 5 (Obigarm–Nurobod) Road Project | Advance Notice | Active | 28 Jun 2019 | |
52042-TAJ: CAREC Corridors 2, 3, and 5 (Obigarm–Nurobod) Road Project | Advance Notice | Active | 28 Jun 2019 |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Contractor Address | Executing Agency | Contract Description | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|---|---|
CONSTRUCTION SUPERVISION CONSULTANT | Grant 0683 | 30 Nov 2020 | JV TEMELSU INTERNATIONAL ENGINEERING SERVICES | XXX XXX TURKEY | Ministry of Transport | 4,398,400.00 | — |
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Central Asia Regional Economic Cooperation Corridors 2, 3, and 5 (Obigarm-Nurobod) Road Project: Procurement Plan | Procurement Plans | Jan 2020 |