Related Projects
Project Name | Improving Public Investment Management Program | ||||||||
Project Number | 52073-001 | ||||||||
Country / Economy | Nauru |
||||||||
Project Status | Closed | ||||||||
Project Type / Modality of Assistance | Grant ND |
||||||||
Source of Funding / Amount |
|
||||||||
Strategic Agendas | Inclusive economic growth |
||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Partnerships Private sector development |
||||||||
Sector / Subsector | Public sector management / Public expenditure and fiscal management - Reforms of state owned enterprises |
||||||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||||||
Description | |||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||
Impact | Effect of the Reform Strengthened fiscal sustainability and public investment management |
Project Outcome | |
---|---|
Description of Outcome | Effect of the Reform Strengthened fiscal sustainability and public investment management |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Public expenditure management improved Public asset management improved Governance of SOEs enhanced |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nation-wide |
Safeguard Categories | |
---|---|
Environment | C |
Involuntary Resettlement | C |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Connell, Jacqueline R. |
Responsible ADB Department | Pacific Department |
Responsible ADB Division | Pacific Liaison and Coordination Office in Sydney, Australia |
Executing Agencies |
Department of Finance [email protected] Yaren District, Republic of Nauru, Central Pacific Department of Finance Yaren District, Republic of Nauru, Central Pacific |
Timetable | |
---|---|
Concept Clearance | 30 Aug 2019 |
Fact Finding | 22 Sep 2019 to 26 Sep 2019 |
MRM | 10 Feb 2020 |
Approval | 03 Jun 2020 |
Last Review Mission | - |
Last PDS Update | 05 Jun 2020 |
Grant 0703-NAU
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
03 Jun 2020 | 11 Jun 2020 | 08 Jul 2020 | 30 Jun 2020 | 10 Sep 2020 | 10 Sep 2020 |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 5.32 | Cumulative Contract Awards | |||
ADB | 5.00 | 17 Jun 2022 | 5.00 | 0.00 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.32 | 17 Jun 2022 | 5.00 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Improving Public Investment Management Program: Program Completion Report | Project/Program Completion Reports | Dec 2021 |
Grant Agreement (Special Operations) for Grant 0703-NAU: Improving Public Investment Management Program | Grant Agreement | Jun 2020 |
Improving Public Investment Management Program: Report and Recommendation of the President | Reports and Recommendations of the President | May 2020 |
Improving Public Investment Management Program: Concept Paper | Concept Papers | Aug 2019 |
Improving Public Investment Management Program: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Jun 2019 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
Title | Document Type | Document Date |
---|---|---|
Nauru: Improving Public Investment Management Program | Validations of Project Completion Reports | Dec 2022 |
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
No tenders for this project were found.
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.