Tajikistan : Reconnection to the Central Asian Power System Project

Sovereign Project | 52122-001

In April 2018, Tajikistan started to export power to Uzbekistan on an islanded mode. However, in order to synchronize the systems and achieve power trade target, the relay protection system in Tajikistan has to be modernized and new interconnection points established. The project will: (i) install modern relays, circuit breakers, instrumental transformers and ancillary equipment and systems at eight 220kV and two 500kV interconnection points; (ii) establish two new 500kV interconnections; and, (iii) provide capacity building to Barki Tojik staff in reliability of parallel operations.

These solutions will result in the following outcome: regional energy resource utilization among CAPS countries improved.

Project Details

Project Name
Reconnection to the Central Asian Power System Project
Project Number
52122-001
Country / Economy
  • Tajikistan
Project Status
Active
Project Type / Modality of Assistance
  • Grant
Source of Funding / Amount
Grant 0622-TAJ: Reconnection to the Central Asian Power System Project
Source Amount
Asian Development Fund US$ 35.00 million
Strategic Agendas
  • Environmentally sustainable growth
  • Inclusive economic growth
  • Regional integration
Drivers of Change
  • Governance and capacity development
Sector / Subsector
  • Energy / Electricity transmission and distribution

Gender
No gender elements
Description

In April 2018, Tajikistan started to export power to Uzbekistan on an islanded mode. However, in order to synchronize the systems and achieve power trade target, the relay protection system in Tajikistan has to be modernized and new interconnection points established. The project will: (i) install modern relays, circuit breakers, instrumental transformers and ancillary equipment and systems at eight 220kV and two 500kV interconnection points; (ii) establish two new 500kV interconnections; and, (iii) provide capacity building to Barki Tojik staff in reliability of parallel operations.

These solutions will result in the following outcome: regional energy resource utilization among CAPS countries improved.

Project Rationale and Linkage to Country/Regional Strategy

The Central Asian republics are endowed with significant energy related natural resources, however, the distribution of these is highly skewed. The Kyrgyz Republic and Tajikistan have abundant hydro resources, while in contrast Kazakhstan, Turkmenistan and Uzbekistan are rich with fossil fuels. During the Soviet Union era these resources were managed at the regional level. Energy systems were designed to take into account the location of various energy sources and needs of entire region. The hydropower resources in Kyrgyz Republic and Tajikistan were operated primarily as an irrigation systems with power generation being secondary. Energy and water infrastructure, inherited by these countries, implicitly contemplated energy and water transfer across administrative boundaries that later have become national borders.

However, the obsolete infrastructure systems in Tajikistan left from the former Soviet Union era that has neither been properly maintained nor replaced, especially during the civil war. This significantly deteriorated the reliability of the protection systems, which is one of the key elements for the parallel operation of the power systems. For the lack of sufficient infrastructure, the Tajikistan system has not been reconnected to the Central Asia Power System (CAPS) since its disconnection in 2009.

In 2017, Tajikistan and Uzbekistan started working together to interconnect the electricity systems. In early 2018, the governments of both countries signed the Memorandum of Understanding according to which Tajikistan will start to exports summer surplus power to Uzbekistan. Initially, vertically integrated state power utility JSC Barki Tojik will start exporting 1.5 TWh on islanded mode in Uzbekistan (asynchronous operation) and after achieving full parallel operation, the export volume will increase to 5 TWh. This project will provide the infrastructure necessary for achieving full parallel operation of the two systems.

Impact

Regional energy trade expanded

Project Outcome

Description of Outcome

Regional energy efficiency among CAPS countries improved.

Progress Toward Outcome
IFBs for EPC contracts for relay protection and emergency control systems issued in June 2020, with bids due in August 2020.

Implementation Progress

Description of Project Outputs

Tajikistan and Uzbekistan electricity grids synchronized

Interconnection between Tajikistan and Uzbekistan expanded

Capacity in Tajikistan for stable parallel operation improved

Status of Implementation Progress (Outputs, Activities, and Issues)

Target deferred to 2022. IFB for EPC contract issued in June 2020, and bids opened in Sep. Contract signing in Q4 2020, and commissioning in Q3 2022.

The EPC contractor will train the PMU, in coordination with the PIC.

Target deferred to 2022. IFB for EPC contract issued in June 2020, with bids opened in Sep. Contract signing will be in Q4 2020, and commissioning in Q3 2022.

Target deferred to 2022. IFB for EPC contract issued in June 2020, with bid opened in Aug. Contract signing will be in Q4 2020, and commissioning in Q3 2022.

Geographical Location
Nation-wide

Safeguard Categories

Environment
B
Involuntary Resettlement
B
Indigenous Peoples
C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Business Opportunities

Consulting Services
A project implementation consulting firm was recruited with an estimated 214 person-months of inputs using quality-and-cost-based selection method (standard quality:cost ratio of 90:10) with international advertising.
Procurement
An engineering, procurement and construction (EPC) contract will be procured for the relay protection system following ADB's open competitive bidding, single-stage: two-envelope bidding procedure, with international advertising. Another EPC contract for the emergency control system will be procured by direct contracting to DS Group in Kazakhstan.

Contact

Responsible ADB Officer
Qubodbekov, Daler
Responsible ADB Department
Sectors Group
Responsible ADB Division
Energy Sector Office (SG-ENE)
Executing Agencies
Open Stock Holding Company "Barqi Tojik"

Timetable

Concept Clearance
26 Jul 2018
Fact Finding
05 Jun 2018 to 13 Jun 2018
MRM
30 Aug 2018
Approval
12 Nov 2018
Last Review Mission
-
Last PDS Update
30 Sep 2020

Funding

Grant 0622-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
12 Nov 2018 23 Nov 2018 20 Feb 2019 28 Feb 2022 28 Dec 2025 -
Financing Plan
  Total (Amount in US$ million)
Project Cost 40.00
ADB 35.00
Counterpart 5.00
Cofinancing 0.00
Grant Utilization
  Date ADB Others Net Percentage
Cumulative Contract Awards 10 Sep 2024 34.81 0.00 99%
Cumulative Disbursements 10 Sep 2024 18.14 0.00 52%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Partly satisfactory Satisfactory Satisfactory - Satisfactory

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Reconnection to the Central Asian Power System Project: Social Monitoring Report (January-June 2024) Social Monitoring Reports Jul 2024
Reconnection to the Central Asian Power System Project: Land Acquisition and Resettlement Plan Implementation Compliance Report Resettlement Plans Apr 2024
Reconnection to the Central Asian Power System Project: Social Due Diligence Report Safeguards Due Diligence Reports Apr 2024
Reconnection to the Central Asian Power System Project: Land Acquisition and Resettlement Plan Resettlement Plans Apr 2024
Reconnection to the Central Asian Power System Project: Social Monitoring Report (July-December 2023) Social Monitoring Reports Mar 2024
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (July-December 2023) Environmental Monitoring Reports Feb 2024
Reconnection to the Central Asian Power System Project: Social Monitoring Report (January-June 2023) Social Monitoring Reports Sep 2023
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (January-June 2023) Environmental Monitoring Reports Sep 2023
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (July-December 2022) Environmental Monitoring Reports Jun 2023
Reconnection to the Central Asian Power System Project: Social Monitoring Report (July-December 2022) Social Monitoring Reports May 2023
Reconnection to the Central Asian Power System Project: Safeguard Due Diligence Report Safeguards Due Diligence Reports May 2023
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (January-June 2022) Environmental Monitoring Reports Dec 2022
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (July-December 2021) Environmental Monitoring Reports May 2022
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (January-June 2021) Environmental Monitoring Reports Nov 2021
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (July-December 2020) Environmental Monitoring Reports Mar 2021
Reconnection to the Central Asian Power System Project: Environmental Monitoring Report (January-June 2020) Environmental Monitoring Reports Sep 2020
Reconnection to Central Asian Power System Project: Initial Environmental Examination Initial Environmental Examination Oct 2018
Reconnection to Central Asian Power System Project: Land Acquisition and Resettlement Plan Resettlement Plans Oct 2018
Reconnection to Central Asian Power System Project: Initial Environment Examination Initial Environmental Examination Aug 2018
Reconnection to Central Asian Power System Project: Land Acquisition and Resettlement Framework Resettlement Frameworks Aug 2018

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Grant 0622-TAJ: Reconnection to Central Asian Power System Project - CORRIGENDUM Invitation for Bids Closed
Grant 0622-TAJ: Reconnection to Central Asian Power System Project - ORIGINAL Invitation for Bids Closed
Project Implementation Consultant Firm - Consulting Closed

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
PACKAGE 1 - RELAY PROTECTION SYSTEM Grant 0622 15 Apr 2021 TBEA CO. LTD. | NO. 189 SOUTH BEIJING ROAD CHANGJI XINJIANG CHINA PEOPLE'S REP. OF OSHC "Barqi Tojik" 12,632,313.40
PROJECT IMPLEMENTATION CONSULTANT Grant 0622 02 Oct 2019 GOPA INTERNATIONAL ENERGY CONSULTANTS GMBH | 61352 BAD HOMBURG GERMANY OSHC "Barqi Tojik" 2,602,710.65

Procurement Plan

Title Document Type Document Date
Reconnection to the Central Asian Power System Project: Procurement Plan Procurement Plans Feb 2023