Indonesia : Sustainable Infrastructure Assistance Program Phase II - Supporting Sustainable and Efficient Energy Policies and Investments (Subproject 2)

Sovereign Project | 52152-002

Project Name
Sustainable Infrastructure Assistance Program Phase II - Supporting Sustainable and Efficient Energy Policies and Investments (Subproject 2)
Project Number
52152-002
Country / Economy
  • Indonesia
Project Status
Active
Project Type / Modality of Assistance
  • Technical Assistance
Source of Funding / Amount
TA 9777-INO: Sustainable Infrastructure Assistance Program Phase II - Supporting Sustainable and Efficient Energy Policies and Investments (Subproject 2)
Source Amount
Government of Australia US$ 1.50 million
TA 9777-INO: Sustainable Infrastructure Assistance Program Phase II - Supporting Sustainable and Efficient Energy Policies and Investments (Subproject 2)
Source Amount
Government of Australia US$ 2.00 million
Strategic Agendas
  • Environmentally sustainable growth
  • Inclusive economic growth
Drivers of Change
  • Gender Equity and Mainstreaming
  • Governance and capacity development
  • Knowledge solutions
  • Partnerships
  • Private sector development
Sector / Subsector
  • Energy / Energy sector development and institutional reform

Gender
Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

Implementation Progress

Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Nation-wide

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Contact

Responsible ADB Officer
Miller, Daniel
Responsible ADB Department
Sectors Group
Responsible ADB Division
Energy Sector Office (SG-ENE)
Executing Agencies
National Development Planning Agency (BAPPENAS)

Timetable

Concept Clearance
-
Fact Finding
-
MRM
-
Approval
05 Aug 2019
Last Review Mission
-
Last PDS Update
25 Nov 2021

Funding

TA 9777-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Aug 2019 05 Aug 2019 05 Aug 2019 31 Dec 2021 31 Dec 2025 -
Financing Plan/TA Utilization
ADB Cofinancing Counterpart Total
Gov Beneficiaries Project Sponsor Others
0.00 3,500,000.00 0.00 0.00 0.00 0.00 3,500,000.00
Cumulative Disbursements
Date Amount
21 Jun 2024 1,742,073.24

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
INO GPGP: Geochemist Individual - Consulting Closed
Clean Energy Advisor Individual - Consulting Closed
Affordable and Sustainable Energy Transition Program Firm - Consulting Closed
Energy Efficiency Specialist Individual - Consulting Closed
HDF: National Social Safeguards Specialist Individual - Consulting Closed
HDF: International Environment Safeguards Specialist Individual - Consulting Closed
International Environmental Management and Biodiversity Specialist Individual - Consulting Closed
International Social Specialist Individual - Consulting Closed
National Gender and Diversity Specialist Individual - Consulting Closed
Energy Efficiency Specialist - Financial Individual - Consulting Closed
Energy Efficiency Specialist - Technical Individual - Consulting Closed
Clean Energy Analyst Individual - Consulting Closed
Gender Specialist Individual - Consulting Closed
Financial Management Specialist Individual - Consulting Closed
Procurement Specialist Individual - Consulting Closed
Clean and Efficient Energy Policy and Finance Analyst Individual - Consulting Closed
Clean Energy Analyst Individual - Consulting Closed
International Energy Policy Analyst Individual - Consulting Closed
Consulting Firm Firm - Consulting Closed

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Project Preparatory Technical Assistance 9777 03 Feb 2020 NIRAS Finland Oy(FINLAND) in association with Institute for Essential Services Reform(INDONESIA) | Ratatie 11, Kr.11 Vantaa, 01300 Finland National Development Planning Agency (BAPPENAS) 1,126,271.00

Procurement Plan

None currently available.