fbpx 52167-001: TAPI Gas Pipeline Project (Phase 1) | Asian Development Bank

Regional: TAPI Gas Pipeline Project (Phase 1)

Sovereign (Public) Project | 52167-001 Status: Proposed

The Governments of Turkmenistan, Afghanistan, and Pakistan have each requested Asian Development Bank (ADB) financing for Phase 1 (the Project) of the TAPI gas pipeline (the TAPI Pipeline). The TAPI Pipeline extends for approximately 1,600 kilometers (km), from the Turkmenistan-Afghanistan border to the Pakistan-India border. At full capacity, the TAPI Pipeline can transport up to 33 billion cubic meters (bcm) of natural gas per year from Turkmenistan to Afghanistan, Pakistan, and India over a commercial operations period of 30 years. The Project comprises the procurement and installation of pipeline and related facilities (without compressor stations) over the entire 1,600 km length within Afghanistan and Pakistan.

Project Details

Project Officer
Pladet, Roland C.J. Central and West Asia Department Request for information
Country
  • Regional
Sector
  • Energy
 
Project Name TAPI Gas Pipeline Project (Phase 1)
Project Number 52167-001
Country Regional
Afghanistan
India
Pakistan
Turkmenistan
Project Status Proposed
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
GU: Turkmenistan-Afghanistan-Pakistan-India (TAPI) Natural Gas Pipeline Project
Ordinary capital resources US$ 500.00 million
Grant: Turkmenistan-Afghanistan-Pakistan-India (TAPI) Natural Gas Pipeline Project
concessional ordinary capital resources lending / Asian Development Fund US$ 100.00 million
Loan: Turkmenistan-Afghanistan-Pakistan-India (TAPI) Natural Gas Pipeline Project
Ordinary capital resources US$ 300.00 million
Ordinary capital resources US$ 100.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Partnerships
Private sector development
Sector / Subsector

Energy / Oil and gas transmission and distribution

Gender Equity and Mainstreaming Some gender elements
Description The Governments of Turkmenistan, Afghanistan, and Pakistan have each requested Asian Development Bank (ADB) financing for Phase 1 (the Project) of the TAPI gas pipeline (the TAPI Pipeline). The TAPI Pipeline extends for approximately 1,600 kilometers (km), from the Turkmenistan-Afghanistan border to the Pakistan-India border. At full capacity, the TAPI Pipeline can transport up to 33 billion cubic meters (bcm) of natural gas per year from Turkmenistan to Afghanistan, Pakistan, and India over a commercial operations period of 30 years. The Project comprises the procurement and installation of pipeline and related facilities (without compressor stations) over the entire 1,600 km length within Afghanistan and Pakistan. In parallel with the Project, (i) State Concern <> will implement with its own resources (including financing from the Islamic Development Bank) the following facilities within Turkmenistan: development of a dedicated portion of the Galkynysh gas field, installation of approximately 200 km of pipeline to the Turkmenistan-Afghanistan border, and construction of one or more compressor stations in Turkmenistan; and (ii) GAIL (India) Limited will implement with its own resources the installation of approximately 10 km of pipeline from its gas network terminus at Fazilka to the Pakistan-India border. With all these facilities, the Project can transport approximately 10 bcm of gas per year.
Project Rationale and Linkage to Country/Regional Strategy Once operational, the TAPI Pipeline will allow Turkmenistan to diversify and expand its gas export markets to the southeast, into Afghanistan, Pakistan, and India. The Central Asia Regional Economic Cooperation (CAREC) Program's Strategy for Regional Cooperation in the Energy Sector has identified the TAPI Pipeline as one of the main links in the inter-energy relationship among CAREC countries. Overall, the TAPI Pipeline will have transformational impact on regional cooperation and will also support other initiatives aimed at increasing growth and economic stability in the region. The Project is aligned with the development strategies of Turkmenistan, Afghanistan, Pakistan and India (TAPI), as reflected in their respective Country Partnership Strategies, and is also consistent with the objectives of ADB's Strategy 2030.
Impact

Improved fiscal position of TKM, AFG and PAK

Regional integration through gas exports from TKM to AFG, PAK and IND

Jobs created in AFG and PAK

Outcome Regional gas market is expanded
Outputs

TAPI Pipeline in AFG and PAK (1,600 km) completed

TAPI Pipeline commissioned and operating

Improved access to solar power in selected districts of Multan and Quetta in Pakistan, and Kandahar in Afghanistan

Geographical Location Afghanistan - Nation-wide; India - Nation-wide; Pakistan - Nation-wide; Turkmenistan - Nation-wide
Safeguard Categories
Environment A
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects The project is classified as A' for environment due to significant land uptake, transboundary nature and crossing of key waterways and areas with high biodiversity value considered as critical habitat. Other impacts related with dust / air emissions, noise generation, occupational and community health and safety are also envisaged during project construction and operation phases.
Involuntary Resettlement Based on information provided by TPCL and its consultants, the project is classified as category A for involuntary resettlement (IR) impacts (due to significant land take, and consequent probable impacts on livelihoods).
Indigenous Peoples Turkmenistan is an ethnically homogeneous state with Turkmens comprising 85% of the population. The provinces in Afghanistan where the pipeline crosses are mainly comprised of Pashtuns. Other major ethnic groups that include Tajik, Hazara, Uzbek and Baloch may also be present in the project area. The two provinces in Pakistan where the pipeline crosses are inhabited by Pashtuns and Baloch. None of these major groups and other ethnic groups along the corridor have been identified as indigenous peoples as defined by the Safeguard Policy Statement (SPS). At this stage, the project is classified as category C for impacts on indigenous peoples (IP).
Stakeholder Communication, Participation, and Consultation
During Project Design The main stakeholders of the project would include local residents who will benefit from improved energy supply, central and local governments specifically in the energy sector in the 4 countries, civil society organizations, and the people to be affected by civil works, specifically in the communities surrounding the planned pipeline in Afghanistan and Pakistan. The potential primary beneficiaries of the project are citizens who will benefit from improved and reliable energy access, as well as the people in Turkmenistan who will benefit from increased revenues from gas exports. The affected groups and individuals will be consulted through focus group discussions and consultation meetings during project design.
During Project Implementation
Business Opportunities
Consulting Services TPCL will be responsible for all project implementation activities, including procurement and award and management of all supply, works, consulting services, and other contracts, as well as ensuring the safeguard requirements of the governments and financing agencies are complied with. A project agreement will be executed between ADB and TPCL (and possibly TVEB if required for PCG transaction purposes) under which TPCL will assume direct obligations to ADB to implement the project. The financing agreements between ADB and Turkmenistan, Afghanistan, and Pakistan, respectively, will include provisions requiring that their respective state owned gas entities (footnote 5), exercise their powers as (indirect) shareholders of TPCL, to ensure that TPCL: (i) implements the project in accordance with the project documentation (including financing agreements, project agreement, and safeguards documents); and (ii) undertakes any other actions required to facilitate project completion (including provision of approvals for project procurement and performing project oversight and monitoring).
Procurement ADB will conduct due diligence on the procurement process, evaluation criteria, and the evaluations to ensure that procurement of the goods and services eligible for ADB financing has been undertaken in a manner consistent with ADB's Procurement Policy (2017, as amended from time to time) and Procurement Regulations for ADB Borrowers (2017, as amended from time to time), including ADB's Core Procurement Principles.
Responsible ADB Officer Pladet, Roland C.J.
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Central Bank of Turkmenistan
22 Bitarap Turkmenistan Street
Ashgabat 744000, Turkmenistan
Ministry of Finance
Pashtunistan Watt,
Kabul,
Islamic Republic of Afghanistan
Ministry of Finance, Revenue and Economic Affairs
Block Q, Pakistan Secretariat
Islamabad, ICT, Pakistan 44000
Timetable
Concept Clearance 18 May 2020
Fact Finding 02 Nov 2020 to 16 Nov 2020
MRM 15 Feb 2021
Approval -
Last Review Mission -
Last PDS Update 22 Jun 2020

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.