Indonesia : Promoting Innovative Financial Inclusion Program (Subprogram 2)

Sovereign Project | 52218-002

Project Name Promoting Innovative Financial Inclusion Program (Subprogram 2)
Project Number 52218-002
Country / Economy Indonesia
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 4249-INO: Promoting Innovative Financial Inclusion Program (Subprogram 2)
Ordinary capital resources US$ 500.00 million
Operational Priorities OP1: Addressing remaining poverty and reducing inequalities
OP2: Accelerating progress in gender equality
OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
OP6: Strengthening governance and institutional capacity
Sector / Subsector

Finance / Inclusive finance

Gender Gender equity theme
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nation-wide
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Jayawardana, Poornima G.W.
Responsible ADB Department Sectors Group
Responsible ADB Division Finance Sector Office (SG-FIN)
Executing Agencies
Fiscal Policy Office-Ministry of Finance
Timetable
Concept Clearance 18 Jan 2024
Fact Finding 10 Mar 2022 to 31 Aug 2022
MRM 20 Sep 2022
Approval 15 Nov 2022
Last Review Mission -
Last PDS Update 15 Nov 2022

Loan 4249-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
15 Nov 2022 28 Dec 2022 07 Feb 2023 30 Nov 2023 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 500.00 Cumulative Contract Awards
ADB 500.00 21 Jul 2023 0.00 0.00 0%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 21 Jul 2023 500.00 0.00 100%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.