52224-001: Total Eren Access M-KAT Solar Power Project | Asian Development Bank

Kazakhstan: Total Eren Access M-KAT Solar Power Project

Nonsovereign (Private) Project | 52224-001 Status: Approved

The project comprises the design, construction, commissioning, and operations and maintenance (O&M) of a 135 megawatt (MW) (direct current) ground-mounted, solar power plant with single axis tracking system (along with associated infrastructure) and grid integration for further electricity sale per a fixed tariff. The project site is in southeastern Kazakhstan, about 3 kilometers (km) south of the town of Shu in the Jambyl Region and will cover 500 hectares. The main project components will include approximately photovoltaic panels, inverters, a substation and a 12 km 220 kilovolts (kV) transmission line to the existing 500kV substation. The total annual output from the project is expected to be 207 gigawatt-hours.

Project Details

Project Officer
Pocheim, Wolfgang Private Sector Operations Department Request for information
Country
  • Kazakhstan
Sector
  • Energy
 
Project Name Total Eren Access M-KAT Solar Power Project
Project Number 52224-001
Borrower/Company M-KAT Green Limited Liability Partnership
Country Kazakhstan
Location Nation-wide
Type or Modality of Assistance
3770 Loan Ordinary capital resources KZT 15,310.00 million Approved
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Partnerships
Private sector development
Sector / Subsector

Energy / Renewable energy generation - solar

Gender Equity and Mainstreaming Some gender elements
Responsible ADB Department Private Sector Operations Department
Responsible ADB Division Infrastructure Finance Division 1
Responsible ADB Officer Pocheim, Wolfgang
Project Sponsor(s) Access Infra Central Asia
Eren Groupe SA
Total Eren SA
Description The project comprises the design, construction, commissioning, and operations and maintenance (O&M) of a 135 megawatt (MW) (direct current) ground-mounted, solar power plant with single axis tracking system (along with associated infrastructure) and grid integration for further electricity sale per a fixed tariff. The project site is in southeastern Kazakhstan, about 3 kilometers (km) south of the town of Shu in the Jambyl Region and will cover 500 hectares. The main project components will include approximately photovoltaic panels, inverters, a substation and a 12 km 220 kilovolts (kV) transmission line to the existing 500kV substation. The total annual output from the project is expected to be 207 gigawatt-hours.
Objectives and Scope ADB's proposed assistance will also have a demonstration effect on other developers and sponsors, thereby helping establish the viability of solar power projects in a country with an emerging solar power sector. ADB's local currency support appropriate for projects of this nature that generate local currency denominated revenues will strengthen the momentum towards long-term local currency financing of renewable energy assets. ADB's assistance will ensure that the project is developed with high environmental and social standards.
Linkage to Country/Regional Strategy The project is consistent with ADB's Strategy 2030, which includes tackling climate change and enhancing environmental sustainability as among the key operational priorities. ADB's support for the project is also in line with its country partnership strategy for Kazakhstan, 2017 2021, as the project will help foster sustainable green growth in response to climate change by promoting the use of renewable energy sources, and support private sector operations in clean and renewable energy. ADB's Energy Policy emphasizes investments in renewable energy projects, private sector participation, and wider access to energy. The project complements the recently approved Samruk-Energy Restructuring and Transformation Project, which has a focus on developing a renewable energy pipeline in the country. This ADB loan will be counted as climate financing and will help achieve ADB's annual climate finance target of $6 billion by 2020.
Safeguard Categories
Environment B
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects An initial environmental examination report has been prepared by an independent consultant. The potential environmental impacts noise, vibration, dust, waste generation, ground contamination, and soil erosion are generally associated with construction activities. These impacts are generally site-specific and short-term and can be effectively managed by implementing good engineering, construction, and housekeeping practices as well as preventive and control measures reflected in the World Bank Group's Environmental, Health, and Safety General Guidelines, as detailed in the site-specific environmental management plans. Occupational health and safety risks will be mitigated through the development of a health and safety plan that will include routine training, monitoring, and the provision of personal protective equipment. Environmental and occupational health and safety provisions, consistent with ADB's Safeguard Policy Statement requirements, will be incorporated into the contractor agreements. The sponsor is required to submit a safeguards and social monitoring report on an annual basis that will include information on the project's environmental and social aspects.
Involuntary Resettlement No involuntary resettlement resulted from its activities.
Indigenous Peoples No impact on indigenous peoples resulted from its activities.
Stakeholder Communication, Participation, and Consultation
Timetable for assistance design, processing and implementation
Concept Clearance 10 Sep 2018
Credit Committee Meeting 23 Nov 2018
Approval 14 Jan 2019
Last PDS Update 15 Jan 2019

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Total Eren Access M-KAT Solar Power Project: Social Compliance Audit Report Environment and Social Compliance Audit Reports Sep 2018
Total Eren Access M-KAT Solar Power Project: Stakeholder Engagement Plan Environmental Assessment and Measures Aug 2018
Total Eren Access M-KAT Solar Power Project: Initial Environmental Examination Initial Environmental Examination Jul 2018

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.