Mongolia : Supporting Renewable Energy Development
The ensuing project is to support the government of Mongolia in expanding renewable energy. In spite of vast renewable energy potential, Mongolia depends on 93% of total electricity production from coal fired thermal power plants. Coal has also been used as the primary source for heating. As a result, the energy sector becomes the major contributor to large greenhouse gas emissions and serious air pollution in the country. The air pollution level in Ulaanbaatar and other towns have become worse than that in cities such as Beijing and New Delhi. UNICEF warned that this has become the public health crisis, especially among children. Nevertheless, the use of coal cannot be reduced to meet growing domestic demand for electricity and heating. To be worse, the peak demand for electricity has almost been reaching to the present generation capacity limit. Under the situation, the country has overcome any power shortfall through more expensive power import from Russia.
Project Details
-
Project Officer
Cowlin, Shannon C.
East Asia Department
Request for information -
Country/Economy
Mongolia -
Sector
- Energy
Related Projects
| Project Name | Supporting Renewable Energy Development | ||||||||
| Project Number | 52240-002 | ||||||||
| Country / Economy | Mongolia |
||||||||
| Project Status | Active | ||||||||
| Project Type / Modality of Assistance | Technical Assistance |
||||||||
| Source of Funding / Amount |
|
||||||||
| Operational Priorities | OP2: Accelerating progress in gender equality OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability OP6: Strengthening governance and institutional capacity |
||||||||
| Sector / Subsector | Energy / Electricity transmission and distribution - Energy efficiency and conservation - Large hydropower generation - Renewable energy generation - geothermal |
||||||||
| Gender | Some gender elements | ||||||||
| Description | The ensuing project is to support the government of Mongolia in expanding renewable energy. In spite of vast renewable energy potential, Mongolia depends on 93% of total electricity production from coal fired thermal power plants. Coal has also been used as the primary source for heating. As a result, the energy sector becomes the major contributor to large greenhouse gas emissions and serious air pollution in the country. The air pollution level in Ulaanbaatar and other towns have become worse than that in cities such as Beijing and New Delhi. UNICEF warned that this has become the public health crisis, especially among children. Nevertheless, the use of coal cannot be reduced to meet growing domestic demand for electricity and heating. To be worse, the peak demand for electricity has almost been reaching to the present generation capacity limit. Under the situation, the country has overcome any power shortfall through more expensive power import from Russia. Thus, the energy security and social and economic impacts have been toward conflicting and complicating situation. To tackle the dilemma, the government issued the State Policy on Energy, 20152030 to increase the share of renewable energy to 20% by 2023 and 30% by 2030. ADB's country partnership strategy and country operations business plan (COBP) for Mongolia responded to this priority to expand renewable energy even in remote and less developed regions, and to enable air quality and carbon footprint improvements. Subsequently, the government's mid-term plan for 20192023 includes concrete activities for renewable energy development. For this purpose, this transaction technical assistance (TA) was programmed for 2019 and the ensuing loan project for 2021 in the COBP, 20202021. Given the strategy and rationale, the following were the intended outputs of the ensuing project: (i)Output 1: Transmission strengthened to help evacuate more renewable energy to grid. (ii)Output 2: Pilot pumped storage hydropower generation assessed for detailed engineering studies. (iii)Output 3: Pilot geothermal heat and power generation assessed for detailed engineering studies. (iv)Output 4: Advance heating technologies deployed. However, given project readiness, the project scope has been revised to focus on the transmission expansion and a cleaner heating pilot. The project impact will be increased renewable energy capacity, and the outcome will be increased and diversified clean energy supply schemes. The ensuing project is estimated to cost $150 million. ADB will consider a project loan of $140.0 million from ADB's ordinary capital resources, and the balance is expected to be supported by cofinanciers and/or the government. |
||||||||
| Project Rationale and Linkage to Country/Regional Strategy | The TA will help the government prepare the project. The TA will refine the project scope by incorporating international best practices, innovative solutions, and conduct technical, safeguards, economic, financial, and other due diligence requirements. | ||||||||
| Impact | |||||||||
| Project Outcome | |
|---|---|
| Description of Outcome | |
| Progress Toward Outcome | |
| Implementation Progress | |
| Description of Project Outputs | |
| Status of Implementation Progress (Outputs, Activities, and Issues) | |
| Geographical Location | Nation-wide |
| Summary of Environmental and Social Aspects | |
|---|---|
| Environmental Aspects | |
| Involuntary Resettlement | |
| Indigenous Peoples | |
| Stakeholder Communication, Participation, and Consultation | |
| During Project Design | |
| During Project Implementation | |
| Responsible ADB Officer | Cowlin, Shannon C. |
| Responsible ADB Department | East Asia Department |
| Responsible ADB Division | EASI |
| Executing Agencies |
Ministry of Energy |
| Timetable | |
|---|---|
| Concept Clearance | - |
| Fact Finding | - |
| MRM | - |
| Approval | 16 Jan 2020 |
| Last Review Mission | - |
| Last PDS Update | 19 Sep 2022 |
TA 9941-MON
| Milestones | |||||
|---|---|---|---|---|---|
| Approval | Signing Date | Effectivity Date | Closing | ||
| Original | Revised | Actual | |||
| 16 Jan 2020 | 11 Feb 2020 | 11 Feb 2020 | 31 Mar 2022 | 30 Sep 2023 | - |
| Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
|---|---|---|---|---|---|---|---|---|
| ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
| Gov | Beneficiaries | Project Sponsor | Others | |||||
| 50,000.00 | 1,300,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,350,000.00 | 30 Jan 2023 | 650,868.23 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
| Title | Document Type | Document Date |
|---|---|---|
| Supporting Renewable Energy Development: Technical Assistance Report | Technical Assistance Reports | Jan 2020 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
| Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
|---|---|---|---|---|---|---|
| Project Preparatory | Technical Assistance 9941 | 10 Jun 2021 | Integration Environment & Energy Gmbh in association with Intelligent Energy Systems Pty Ltd | Bahnhofstrasse 9 Graefenberg 91322 Germany | Ministry of Energy | 674,000.00 | — |
Procurement Plan