Kyrgyz Republic : Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit

Sovereign Project | 52256-006

The first activity under the facility will support the physical upgrade of the chlorine neutralization unit at the Osh-Plotina WTP, completed in September 2016 under the Emergency Assistance for Recovery and Reconstruction project. The unit will be upgraded to a higher international standard and provide 400,000 people with access to safe and reliable water supply. The activity will improve the development impact and sustainability of the project.

Project Name
Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit
Project Number
52256-006
Country / Economy
  • Kyrgyz Republic
Project Status
Closed
Project Type / Modality of Assistance
  • Grant
Source of Funding / Amount
Grant 0704-KGZ: Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit
Source Amount
Asian Development Fund US$ 315,829.64
Operational Priorities
  • OP1: Addressing remaining poverty and reducing inequalities
  • OP2: Accelerating progress in gender equality
  • OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
  • OP4: Making cities more livable
  • OP5: Promoting rural development and food security
  • OP6: Strengthening governance and institutional capacity
  • OP7: Fostering regional cooperation and integration
Sector / Subsector
  • Water and other urban infrastructure and services / Urban water supply

Gender
Description
The first activity under the facility will support the physical upgrade of the chlorine neutralization unit at the Osh-Plotina WTP, completed in September 2016 under the Emergency Assistance for Recovery and Reconstruction project. The unit will be upgraded to a higher international standard and provide 400,000 people with access to safe and reliable water supply. The activity will improve the development impact and sustainability of the project.
Project Rationale and Linkage to Country/Regional Strategy
The facility will deliver on CPS, 2018-2022 priorities by (i) supporting early design work and advanced procurement actions to alleviate project start-up bottlenecks, (ii) strengthening the government's project implementation capacity, (iii) introducing new technologies, standards, and management approaches, (iv) enhancing the sustainability of ADB-financed investments through improved asset management practices, and (v) bringing completed infrastructure investments in conformance with up-to-date performance standards.
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

Implementation Progress

Description of Project Outputs

Project efficiency and sustainability enhanced

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Safeguard Categories

Environment
B
Involuntary Resettlement
C
Indigenous Peoples
C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Contact

Responsible ADB Officer
Amanova, Ainagul
Responsible ADB Department
Central and West Asia Department
Responsible ADB Division
Kyrgyz Resident Mission (KYRM)
Executing Agencies
Ministry of Finance

Timetable

Concept Clearance
01 Oct 2021
Fact Finding
20 May 2019 to 24 May 2019
MRM
16 Jul 2019
Approval
17 Aug 2020
Last Review Mission
-
Last PDS Update
10 Jun 2020

Funding

Grant 0704-KGZ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Aug 2020 17 Nov 2020 17 Nov 2020 31 May 2022 - 27 Sep 2021
Financing Plan
  Total (Amount in US$ million)
Project Cost 0.44
ADB 0.32
Counterpart 0.13
Cofinancing 0.00
Grant Utilization
  Date ADB Others Net Percentage
Cumulative Contract Awards 10 Nov 2023 0.32 0.00 100%
Cumulative Disbursements 10 Nov 2023 0.32 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory - - - -

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.


Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Kyrgyz Republic: Osh–Plotina Water Treatment Plant Validations of Project Completion Reports Dec 2023

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Supervision Engineer Individual - Consulting Closed
NATIONAL PROJECT MANAGEMENT SPECIALIST Individual - Consulting Closed
52256-KGZ: Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit [SEFF-CNU-OCB-G-01] Invitation for Bids Closed

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

Title Document Type Document Date
Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit: Procurement Plan Procurement Plans Feb 2021