fbpx 52256-006: Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit | Asian Development Bank

Kyrgyz Republic: Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit

Sovereign (Public) Project | 52256-006 Status: Approved

The first activity under the facility will support the physical upgrade of the chlorine neutralization unit at the Osh-Plotina WTP, completed in September 2016 under the Emergency Assistance for Recovery and Reconstruction project. The unit will be upgraded to a higher international standard and provide 400,000 people with access to safe and reliable water supply. The activity will improve the development impact and sustainability of the project.

 
Project Name Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit
Project Number 52256-006
Country Kyrgyz Republic
Project Status Approved
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0704-KGZ: Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit
concessional ordinary capital resources lending / Asian Development Fund US$ 500,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change
Sector / Subsector

Water and other urban infrastructure and services / Urban water supply

Gender Equity and Mainstreaming
Description The first activity under the facility will support the physical upgrade of the chlorine neutralization unit at the Osh-Plotina WTP, completed in September 2016 under the Emergency Assistance for Recovery and Reconstruction project. The unit will be upgraded to a higher international standard and provide 400,000 people with access to safe and reliable water supply. The activity will improve the development impact and sustainability of the project.
Project Rationale and Linkage to Country/Regional Strategy The facility will deliver on CPS, 2018-2022 priorities by (i) supporting early design work and advanced procurement actions to alleviate project start-up bottlenecks, (ii) strengthening the government's project implementation capacity, (iii) introducing new technologies, standards, and management approaches, (iv) enhancing the sustainability of ADB-financed investments through improved asset management practices, and (v) bringing completed infrastructure investments in conformance with up-to-date performance standards.
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs Project efficiency and sustainability enhanced
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Amanova, Ainagul
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Kyrgyz Resident Mission
Executing Agencies
Ministry of Finance
Public Debt Department Room 500
58 Erkindik Boulevard
Bishkek 720040, Kyrgzy Republic
Timetable
Concept Clearance 01 Oct 2021
Fact Finding 20 May 2019 to 24 May 2019
MRM 16 Jul 2019
Approval 17 Aug 2020
Last Review Mission -
Last PDS Update 10 Jun 2020

Grant 0704-KGZ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Aug 2020 - - 31 May 2022 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 0.63 Cumulative Contract Awards
ADB 0.50 17 Aug 2020 0.00 0.00 0%
Counterpart 0.13 Cumulative Disbursements
Cofinancing 0.00 17 Aug 2020 0.00 0.00 0%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Supervision Engineer Individual - Consulting Closed 20 Jun 2020 15 Jul 2020
NATIONAL PROJECT MANAGEMENT SPECIALIST Individual - Consulting Closed 20 Jun 2020 15 Jul 2020
52256-KGZ: Osh-Plotina Water Treatment Plant Chlorine Neutralization Unit [SEFF-CNU-OCB-G-01] Invitation for Bids Closed 01 Jun 2020 15 Jul 2020

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.