Kyrgyz Republic : Project Readiness for the Issyk-Kul Environmental Management and Sustainable Tourism Development

Sovereign Project | 52256-008

SEFF Activity 3 for Project Readiness for the Issyk-Kul Environmental Management and Sustainable Tourism Development will finance project preparation activities for the Issyk-Kul Environmental Management and Sustainable Tourism Development Project (the Issyk-Kul project), namely: (i) the consulting services (firm) for the preparation of preliminary design and detailed engineering design (DED) for the Issyk-Kul project, and (ii) the consulting services (individual consultants) to support the project management unit (PMU) for the implementation of Activity 3 and the start-up activities of Issyk-Kul project (implementation support consultants).

Project Details

  • Project Officer
    Hong, Heeyoung
    Central and West Asia Department
    Request for information
  • Country/Economy
    Kyrgyz Republic
  • Sector
    • Water and other urban infrastructure and services
Project Name Project Readiness for the Issyk-Kul Environmental Management and Sustainable Tourism Development
Project Number 52256-008
Country / Economy Kyrgyz Republic
Project Status Active
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0835-KGZ: Project Readiness for the Issyk-Kul Environmental Management and Sustainable Tourism Development
Asian Development Fund US$ 1.50 million
Operational Priorities OP1: Addressing remaining poverty and reducing inequalities
OP4: Making cities more livable
Sector / Subsector

Water and other urban infrastructure and services / Other urban services - Urban sanitation - Urban sewerage

Gender
Description SEFF Activity 3 for Project Readiness for the Issyk-Kul Environmental Management and Sustainable Tourism Development will finance project preparation activities for the Issyk-Kul Environmental Management and Sustainable Tourism Development Project (the Issyk-Kul project), namely: (i) the consulting services (firm) for the preparation of preliminary design and detailed engineering design (DED) for the Issyk-Kul project, and (ii) the consulting services (individual consultants) to support the project management unit (PMU) for the implementation of Activity 3 and the start-up activities of Issyk-Kul project (implementation support consultants).
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs

Project efficiency and sustainability enhanced.

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Hong, Heeyoung
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Urban Development and Water Division, CWRD
Executing Agencies
State Agency for Architecture, Construction and Communal Services
Timetable
Concept Clearance -
Fact Finding 02 Nov 2021 to 02 Nov 2021
MRM -
Approval 23 May 2022
Last Review Mission -
Last PDS Update 24 May 2022

Grant 0835-KGZ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
23 May 2022 19 Jul 2022 20 Jul 2022 30 Jun 2025 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 1.50 Cumulative Contract Awards
ADB 1.50 24 Apr 2023 1.39 0.00 93%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 24 Apr 2023 0.26 0.00 18%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Water Supply and Sanitation Specialist for tourism and culture facilities Individual - Consulting Closed
National Urban architect Individual - Consulting Closed
National Resettlement Expert Individual - Consulting Closed
Detailed Engineering Design Consultants Firm - Consulting Closed
: Project Management and Construction Supervision Consultancy (PMCSC) (Loan/Grant Implementation Consultants) Firm - Consulting Active

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Detailed Engineering Design Consulting Services Grant 0835 08 Aug 2022 JV of Egis International France and Egis Water and Maritime France | 33 avenue du maine 75 755 Paris Cedex 15 State Agency for Architecture, Construction and Communal Services 1,301,600.00

Procurement Plan

None currently available.