Timor-Leste : Presidente Nicolau Lobato International Airport Expansion Project

Sovereign Project | 52320-002

The Presidente Nicolau Lobato International Airport (PNLIA) has a runway of 1,850 meters (m) in length with a pavement width of 30m. The runway can accommodate Code C aircrafts such as B737 and A320, but operations of these aircrafts are under significant restrictions on payload because the length of the runway is short. The existing runway also does not have the ICAO specified Runway End Safety Areas (RESA), which is at least 90m long and required for safe aerodrome operation. These two issues pose challenges in route development of the PNLIA for better air connectivity of the country because airlines have to take into consideration commercial penalty by operating with reduced passenger load factors (i.e., less seat occupied) and consider extra safety measures. The current Air Traffic Control Tower (ATCT) is also in poor condition and does not fully meet the requirements even for the existing runway.

Project Details

  • Project Officer
    Shim, Chaorin
    Southeast Asia Department
    Request for information
  • Country/Economy
    Timor-Leste
  • Sector
    • Transport
Project Name Presidente Nicolau Lobato International Airport Expansion Project
Project Number 52320-002
Country / Economy Timor-Leste
Project Status Active
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
Grant: Presidente Nicolau Lobato International Airport Expansion Project
Japan International Cooperation Agency US$ 44.00 million
Loan 4104-TIM: Presidente Nicolau Lobato International Airport Expansion Project
Ordinary capital resources US$ 85.00 million
Loan 4105-TIM: Presidente Nicolau Lobato International Airport Expansion Project
Concessional ordinary capital resources lending US$ 50.00 million
Operational Priorities OP2: Accelerating progress in gender equality
OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
OP6: Strengthening governance and institutional capacity
OP7: Fostering regional cooperation and integration
Sector / Subsector

Transport / Air transport

Gender Some gender elements
Description

The Presidente Nicolau Lobato International Airport (PNLIA) has a runway of 1,850 meters (m) in length with a pavement width of 30m. The runway can accommodate Code C aircrafts such as B737 and A320, but operations of these aircrafts are under significant restrictions on payload because the length of the runway is short. The existing runway also does not have the ICAO specified Runway End Safety Areas (RESA), which is at least 90m long and required for safe aerodrome operation. These two issues pose challenges in route development of the PNLIA for better air connectivity of the country because airlines have to take into consideration commercial penalty by operating with reduced passenger load factors (i.e., less seat occupied) and consider extra safety measures. The current Air Traffic Control Tower (ATCT) is also in poor condition and does not fully meet the requirements even for the existing runway.

The project will be aligned with the following impact: national productivity improved by ensuring better connectivity of its people within and outside of the country. The proposed outcome is improved efficiency and safety of goods' and people's movements.

Project Rationale and Linkage to Country/Regional Strategy The proposed project will improve the facilities at the PNLIA in Dili mainly by upgrading the airport runway to meet the requirements recommended by the International Civil Aviation Organization, and configuring other airport facilities to conform to the upgraded runway. The project will enhance the safety of the PNLIA and reduce safety concerns on the airport key facilities raised by the market, which will help the country establish better air connectivity.
Impact

Economic diversification and national productivity improved by ensuring better connectivity within and outside of the country

Project Outcome
Description of Outcome

Efficiency and safety of goods' and people's movements improved

Progress Toward Outcome The loans became effective on 14 December 2021. Procurement of one civil works package through open-competitive bidding with prequalification is ongoing in parallel with the recruitment of the construction supervision consultant.
Implementation Progress
Description of Project Outputs

PNLIA runway, air traffic control tower, and other key airport facilities improved

Organizational and management capacity of the IPMU and the MOTC (ANATL and AACTL) enhanced

Status of Implementation Progress (Outputs, Activities, and Issues)

Not due to start.

Recruitment of construction supervision consultant and procurement of civil works contractor are ongoing.

Not due to start.

Recruitment of construction supervision consultant and procurement of civil works contractor are ongoing.

Not due to start.

Recruitment of construction supervision consultant and procurement of civil works contractor are ongoing.

Not due to start.

Recruitment of construction supervision consultant and procurement of civil works contractor are ongoing.

Not due to start.

Recruitment of construction supervision consultant and procurement of civil works contractor are ongoing.

Geographical Location Nation-wide
Safeguard Categories
Environment A
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Shim, Chaorin
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Transport and Communications Division, SERD
Executing Agencies
Council for Administration of the Infrastructure Fund
Timetable
Concept Clearance 22 Dec 2020
Fact Finding 22 Feb 2021 to 09 Mar 2021
MRM 09 Apr 2021
Approval 02 Sep 2021
Last Review Mission -
Last PDS Update 01 Dec 2022

Loan 4104-TIM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
02 Sep 2021 01 Oct 2021 14 Dec 2021 30 Nov 2026 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 115.00 Cumulative Contract Awards
ADB 85.00 20 Apr 2023 0.00 0.00 0%
Counterpart 30.00 Cumulative Disbursements
Cofinancing 0.00 20 Apr 2023 0.16 0.00 0%

Loan 4105-TIM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
02 Sep 2021 01 Oct 2021 14 Dec 2021 30 Nov 2026 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 50.00 Cumulative Contract Awards
ADB 50.00 20 Apr 2023 0.00 0.00 0%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 20 Apr 2023 0.00 0.00 0%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.


Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

Title Document Type Document Date
Presidente Nicolau Lobato International Airport Expansion Project: Procurement Plan Procurement Plans Aug 2021