China, People's Republic of : Shandong West Jining Water Supply and Drainage Integration Program
The proposed program will be the first sector development program (SDP) for the water sector in the PRC and the first ADB SDP implemented at a county level. The SDP aims to address the water sector needs and development constraints of Jiaxiang County, an extremely water sensitive area in the People's Republic of China (PRC), by (i) addressing the policy and institutional gaps and mitigating climate risks, (ii) integrating water supply and delivery of sewerage services, (iii) improving public health and environmental quality of waterways, and (iv) enhancing institutional and program management capacity, under an integrated and long-term approach, where policy and institutional reforms and infrastructure investments are required.
Project Details
-
Project Officer
Zheng, Baochang
East Asia Department
Request for information -
Country/Economy
China, People's Republic of -
Sector
- Agriculture, natural resources and rural development
Project Name | Shandong West Jining Water Supply and Drainage Integration Program | ||||||||
Project Number | 53059-001 | ||||||||
Country / Economy | China, People's Republic of |
||||||||
Project Status | Active | ||||||||
Project Type / Modality of Assistance | Loan |
||||||||
Source of Funding / Amount |
|
||||||||
Operational Priorities | OP1: Addressing remaining poverty and reducing inequalities OP2: Accelerating progress in gender equality OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability OP4: Making cities more livable OP5: Promoting rural development and food security OP6: Strengthening governance and institutional capacity |
||||||||
Sector / Subsector |
Agriculture, natural resources and rural development / Rural sanitation - Rural water policy, institutional and capacity development - Rural water supply services - Water-based natural resources management Public sector management / Reforms of state owned enterprises Water and other urban infrastructure and services / Urban policy, institutional and capacity development - Urban sewerage - Urban water supply |
||||||||
Gender | Effective gender mainstreaming | ||||||||
Description | The proposed program will be the first sector development program (SDP) for the water sector in the PRC and the first ADB SDP implemented at a county level. The SDP aims to address the water sector needs and development constraints of Jiaxiang County, an extremely water sensitive area in the People's Republic of China (PRC), by (i) addressing the policy and institutional gaps and mitigating climate risks, (ii) integrating water supply and delivery of sewerage services, (iii) improving public health and environmental quality of waterways, and (iv) enhancing institutional and program management capacity, under an integrated and long-term approach, where policy and institutional reforms and infrastructure investments are required. | ||||||||
Project Rationale and Linkage to Country/Regional Strategy | Jiaxiang County is one of the most water sensitive areas in the PRC and faces water security issues related to water supply, safe sanitation, floods, and environmental degradation, which are aggravated by rapid urbanization and climate change. Previous interventions have been piecemeal and significant institutional reforms are needed to operationalize the integrated water management policies to deliver sustainable and resilient water services. The proposed program will combine infrastructure investments and institutional reforms to support the achievement of difficult and complex reforms and ensure that an adequate policy and institutional framework is in place for effective implementation of the investment lending, which both will ensure more efficient utilization of water resources and will lead to strategic investments infrastructure and water resources development to meet growing water demands. | ||||||||
Impact | Integrated water management infrastructure and governance strengthened??Urban-rural integration strengthened??Human health and well-being and environmental quality of waterways in Jiaxiang County improved?? |
Project Outcome | |
---|---|
Description of Outcome | Sustainability, affordability, and safety in water and wastewater management services improved?? |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Water sector strategies and operations strengthened??Sustainable water supply with diverse water sources and smart technology established??Wastewater services expanded and improved with smart technology??Institutional and program management capacity enhanced?? |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Jiaxiang Xian |
Safeguard Categories | |
---|---|
Environment | B |
Involuntary Resettlement | B |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | To be determined during project processing |
Involuntary Resettlement | To be determined during project processing |
Indigenous Peoples | To be determined during project processing |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | To be determined during project processing |
During Project Implementation | To be determined during project processing |
Business Opportunities | |
---|---|
Consulting Services | Consultants were engaged either as individual or through a firm using the Fixed budget selection and output TOR. The TA will indicatively require eight areas of expertise, and a total of 31 person-months consulting inputs (13 person-months, international and 18 person-months, national). |
Responsible ADB Officer | Zheng, Baochang |
Responsible ADB Department | East Asia Department |
Responsible ADB Division | PRC Resident Mission |
Executing Agencies |
Jiaxiang Country Government |
Timetable | |
---|---|
Concept Clearance | 22 Aug 2019 |
Fact Finding | 07 Apr 2021 to 26 Apr 2021 |
MRM | 27 Aug 2021 |
Approval | 23 Sep 2022 |
Last Review Mission | - |
Last PDS Update | 23 Sep 2022 |
Loan 4219-PRC
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
23 Sep 2022 | 21 Dec 2022 | 20 Apr 2023 | 30 Sep 2028 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 184.24 | Cumulative Contract Awards | |||
ADB | 72.00 | 05 May 2023 | 0.05 | 0.00 | 0% |
Counterpart | 112.24 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 05 May 2023 | 0.00 | 0.00 | 0% |
Loan 4220-PRC
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
23 Sep 2022 | 21 Dec 2022 | 20 Apr 2023 | 30 Jun 2026 | - | - |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 28.00 | Cumulative Contract Awards | |||
ADB | 28.00 | 05 May 2023 | 0.00 | 0.00 | 0% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 05 May 2023 | 0.00 | 0.00 | 0% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
Title | Document Type | Document Date |
---|---|---|
Shandong West Jining Water Supply and Drainage Integration Program: Resettlement Plan | Resettlement Plans | Jul 2021 |
Shandong West Jining Water Supply and Drainage Integration Program: Initial Environmental Examination | Initial Environmental Examination | Jul 2021 |
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
ADB to Help Improve Water and Wastewater Management in Jiaxiang County, PRC
ADB has approved a $100 million loan to help improve sustainability, affordability, and safety in water and wastewater management services in Jiaxiang County, the People’s Republic of China.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Start-up Consultant - Project management and procurement specialist | Individual - Consulting | Closed |
Contracts Awarded
Procurement Plan
Title | Document Type | Document Date |
---|---|---|
Shandong West Jining Water Supply and Drainage Integration Program: Procurement Plan | Procurement Plans | Mar 2023 |