Project Name | Rural Vitalization—Rural Wastewater Treatment and Environmental Management | ||||||
Project Number | 53088-001 | ||||||
Country | China, People's Republic of |
||||||
Project Status | Active | ||||||
Project Type / Modality of Assistance | Technical Assistance |
||||||
Source of Funding / Amount |
|
||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth |
||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Knowledge solutions Partnerships Private sector development |
||||||
Sector / Subsector | Agriculture, natural resources and rural development / Rural sanitation - Rural water policy, institutional and capacity development |
||||||
Gender Equity and Mainstreaming | Some gender elements | ||||||
Description | |||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||
Impact | Rural vitalization strategy mainstreamed in rural areas of the PRC. |
Project Outcome | |
---|---|
Description of Outcome | Sustainable and innovative solutions for rural sanitation, wastewater, and SWM in the PRC developed. |
Progress Toward Outcome | On-track to achieve outcome. |
Implementation Progress | |
Description of Project Outputs | Rural vitalization initiatives (including rural sanitation, wastewater, and SWM) supported. |
Status of Implementation Progress (Outputs, Activities, and Issues) | The inception report was submitted in August 2020. Output 1. The design of RWWM online website has been submitted in Q1 2021. The draft final RWWM guideline is for submission by Q3 2021. Output 2. The draft interim report is for submission by Q1 2021. Output 3. The draft interim report has been submitted in Q1 2021. The draft final report is for submission by Q2 2021. |
Geographical Location | Nation-wide |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | Public authority, private sector, and relevant stakeholders were consulted during the project design stage. |
During Project Implementation | During the inception mission, public authority, private sector, and relevant stakeholders were consulted during the workshop. |
Business Opportunities | |
---|---|
Consulting Services | ADB will engage a consulting firm and/or individual consultants following the ADB Procurement Policy (2017, as amended from time to time) and its associated project administration instructions and TA staff instructions using a simplified technical proposal and the quality- and cost-based selection method. The quality cost ratio will be 90:10 because of the high technical complexity of the consulting assignment. |
Procurement | ADB will engage a consulting firm and/or individual consultants following the ADB Procurement Policy (2017, as amended from time to time) and its associated project administration instructions and TA staff instructions. |
Responsible ADB Officer | Fan, Mingyuan |
Responsible ADB Department | East Asia Department |
Responsible ADB Division | Environment, Natural Resources & Agriculture Division, EARD |
Executing Agencies |
Asian Development Bank 6 ADB Avenue, Mandaluyong City 1550, Philippines Bureau of Finance, Shanxi Province 345 Yung Ze Avenue Taiyuan City 030001, Shanxi Finance Department Henan Province 25 Jingsan Road Jinshui District, Zhengzhou China, 450008 National Development and Reform Commission No. 38 South Yuetan St. Beijing 100824 China |
Timetable | |
---|---|
Concept Clearance | 29 May 2019 |
Fact Finding | 17 Jun 2019 to 21 Jun 2019 |
MRM | - |
Approval | 14 Oct 2019 |
Last Review Mission | - |
Last PDS Update | 30 Mar 2021 |
TA 9825-PRC
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
14 Oct 2019 | 09 Nov 2019 | 09 Nov 2019 | 31 Dec 2021 | - | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
600,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,100,000.00 | 14 Oct 2019 | 54,777.25 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Rural Vitalization—Rural Wastewater Treatment and Environmental Management: Technical Assistance Report | Technical Assistance Reports | Oct 2019 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Information and Communication Technology Specialist | Individual - Consulting | Closed | 02 Apr 2020 | 08 Apr 2020 |
Regulation and Institutional Specialist | Individual - Consulting | Closed | 02 Apr 2020 | 08 Apr 2020 |
Institutional Specialist/Coordinator | Individual - Consulting | Closed | 02 Apr 2020 | 08 Apr 2020 |
Rural Wastewater Management Specialist | Individual - Consulting | Closed | 07 Mar 2020 | 13 Mar 2020 |
Information Technology Engineer | Individual - Consulting | Closed | 06 Mar 2020 | 12 Mar 2020 |
Rural Wastewater Process Design Engineer | Individual - Consulting | Closed | 04 Mar 2020 | 10 Mar 2020 |
Financial Management Specialist | Individual - Consulting | Closed | 15 Jan 2020 | 21 Jan 2020 |
Rural Wastewater Management Specialist | Individual - Consulting | Closed | 07 Jan 2020 | 13 Jan 2020 |
Rural Community Specialist | Individual - Consulting | Closed | 20 Dec 2019 | 26 Dec 2019 |
Rural Management Specialist | Individual - Consulting | Closed | 20 Dec 2019 | 26 Dec 2019 |
Rural Development Specialist | Individual - Consulting | Closed | 20 Dec 2019 | 26 Dec 2019 |
Rural Wastewater Design Engineer | Individual - Consulting | Closed | 11 Dec 2019 | 17 Dec 2019 |
Rural Sanitation and Wastewater Management Specialist | Individual - Consulting | Closed | 11 Dec 2019 | 17 Dec 2019 |
Municipal Solid Waste Management Specialist | Individual - Consulting | Closed | 11 Dec 2019 | 17 Dec 2019 |
Municipal Solid Waste Management Specialist | Individual - Consulting | Closed | 11 Dec 2019 | 17 Dec 2019 |
Contracts Awarded
No contracts awarded for this project were found
Procurement Plan
None currently available.