fbpx 53351-001: Preparing Urban Service Improvement Projects | Asian Development Bank

Marshall Islands: Preparing Urban Service Improvement Projects

Sovereign (Public) Project | 53351-001 Status: Approved

Project Details

Project Officer
Yuki Ikeda Pacific Department Request for information
Country
  • Marshall Islands
Sector
  • Water and other urban infrastructure and services
 
Project Name Preparing Urban Service Improvement Projects
Project Number 53351-001
Country Marshall Islands
Project Status Approved
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 6028-RMI: Preparing the Waste and Sanitation and Solid Waste Management Projects (Project Readiness Financing)
concessional ordinary capital resources lending / Asian Development Fund US$ 5.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Partnerships
Sector / Subsector

Water and other urban infrastructure and services / Urban policy, institutional and capacity development - Urban sewerage - Urban solid waste management - Urban water supply

Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nation-wide
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Yuki Ikeda
Responsible ADB Department Pacific Department
Responsible ADB Division PAUW
Executing Agencies
Ministry of Finance
P.O. Box D, Majuro
MH 96960
Republic of the Marshall Islands
Timetable
Concept Clearance -
Fact Finding 29 Oct 2019 to 01 Nov 2019
MRM 27 Nov 2019
Approval 19 Dec 2019
Last Review Mission -
Last PDS Update 23 Jan 2020

Grant 6028-RMI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
19 Dec 2019 - - 31 Jul 2023 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 5.50 Cumulative Contract Awards
ADB 5.00 19 Dec 2019 0.00 0.00 0%
Counterpart 0.50 Cumulative Disbursements
Cofinancing 0.00 19 Dec 2019 0.00 0.00 0%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

None currently available.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Solid Waste Management Project Preparation Assistance (PPA) for Kwajalein Atoll Local Government Firm - Consulting Active 11 Jan 2020 09 Feb 2020

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.