Mongolia : Preparatory Work for Country Partnership Strategy
Project Details
-
Project Officer
Magee, Declan F.
East Asia Department
Request for information -
Country/Economy
Mongolia -
Sector
- Public sector management
Project Name | Preparatory Work for Country Partnership Strategy | ||||
Project Number | 53404-001 | ||||
Country / Economy | Mongolia |
||||
Project Status | Closed | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Operational Priorities | OP2: Accelerating progress in gender equality OP6: Strengthening governance and institutional capacity |
||||
Sector / Subsector | Public sector management / Economic affairs management - Public administration |
||||
Gender | Some gender elements | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | |||||
Impact | Inclusive development in Mongolia enhanced |
Project Outcome | |
---|---|
Description of Outcome | CPS, with broad stakeholder buy-in approved. |
Progress Toward Outcome | CPS Final Review finalized and IED has also finished the the validation. Nine consultations have been held with civil society in 8 different thematic areas. All background assessments have been prepared. Consultations have been undertaken with the government, development partners and the private sector. All preparatory work for the CPS has been finalized and the CPS has been approved by the ADB Board. Final activities under the TA are being finalized including translation of all documents and advisory support to the government in critical areas including the investment climate. |
Implementation Progress | |
Description of Project Outputs | Comprehensive analysis to inform the CPS conducted Feedback and advice from key stakeholders received. |
Status of Implementation Progress (Outputs, Activities, and Issues) | CPS Final Review finalized and IED has also finished the the validation. Nine consultations have been held with civil society in 8 different thematic areas. All background assessments have been prepared. Consultations have been undertaken with the government, development partners and the private sector. All preparatory work for the CPS has been finalized and the CPS has been approved by the ADB Board. Final activities under the TA are being finalized including translation of all documents and advisory support to the government in critical areas including the investment climate. |
Geographical Location | Nation-wide |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | ADB consulted government and the newly appointed CSO Advisory Committee. |
During Project Implementation | Two consultations have taken place on the CPS Final Review. 9 consultations have been held with civil society in 8 different thematic areas (including one on the final review). |
Responsible ADB Officer | Magee, Declan F. |
Responsible ADB Department | East Asia Department |
Responsible ADB Division | Mongolia Resident Mission |
Executing Agencies |
Asian Development Bank |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | 18 Nov 2019 to 18 Nov 2019 |
MRM | - |
Approval | 04 Dec 2019 |
Last Review Mission | - |
Last PDS Update | 22 Sep 2021 |
TA 9885-MON
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
04 Dec 2019 | - | 04 Dec 2019 | 31 Mar 2021 | 30 Sep 2021 | 22 Dec 2021 |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
225,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 225,000.00 | 19 Aug 2022 | 214,643.07 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Preparatory Work for Country Partnership Strategy: Technical Assistance Completion Report | TA Completion Reports | Aug 2022 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.