The transaction technical assistance (TA) facility will provide project preparation support, project implementation support, capacity building, and policy advice to a series of ongoing and ensuing projects in the agriculture, natural resources, and rural development (ANR) sector in the developing member countries (DMCs) in Southeast Asia in line with Strategy 2030 during 2020 -2023.
Project Name | Southeast Asia Agriculture, Natural Resources and Rural Development Facility – Phase II | ||||||||||||||
Project Number | 54002-001 | ||||||||||||||
Country | Regional Cambodia Lao People's Democratic Republic Myanmar Philippines |
||||||||||||||
Project Status | Active | ||||||||||||||
Project Type / Modality of Assistance | Technical Assistance |
||||||||||||||
Source of Funding / Amount |
|
||||||||||||||
Strategic Agendas | Environmentally sustainable growth Inclusive economic growth Regional integration |
||||||||||||||
Drivers of Change | Gender Equity and Mainstreaming Governance and capacity development Partnerships Private sector development |
||||||||||||||
Sector / Subsector | Agriculture, natural resources and rural development / Agricultural policy, institutional and capacity development - Agricultural production - Irrigation - Livestock |
||||||||||||||
Gender Equity and Mainstreaming | Effective gender mainstreaming | ||||||||||||||
Description | The transaction technical assistance (TA) facility will provide project preparation support, project implementation support, capacity building, and policy advice to a series of ongoing and ensuing projects in the agriculture, natural resources, and rural development (ANR) sector in the developing member countries (DMCs) in Southeast Asia in line with Strategy 2030 during 2020 -2023. | ||||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | The ANR sector plays a key role in ensuring inclusive economic growth in the region and has high priority in the respective national development strategies. The TA facility approach will enhance efficiency in project preparation and administration by (i) reducing time and effort for TA processing, approval, and administration; and (ii) accelerating the consultant recruitment process by prequalifying consultants for all the project preparation and implementation support under the facility. | ||||||||||||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Cambodia - Nation-wide; Lao People's Democratic Republic - Nation-wide; Myanmar - Nation-wide; Philippines - Nation-wide |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Leitner, Matthias |
Responsible ADB Department | Southeast Asia Department |
Responsible ADB Division | Environment, Natural Resources & Agriculture Division, SERD |
Executing Agencies |
Asian Development Bank 6 ADB Avenue, Mandaluyong City 1550, Philippines Ministry of Agriculture and Rural Development Room 305 Building A15 10 Nugen Cong Hoan Street Ba Dinh District, Hanoi, Vietnam |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | - |
Approval | 29 Apr 2020 |
Last Review Mission | - |
Last PDS Update | 01 Sep 2020 |
TA 9971-REG
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
29 Apr 2020 | - | 29 Apr 2020 | 30 Apr 2025 | - | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
4,200,000.00 | 1,850,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,050,000.00 | 29 Apr 2020 | 0.00 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title![]() |
Document Type | Document Date |
---|---|---|
Southeast Asia Agriculture, Natural Resources and Rural Development Facility – Phase II: Technical Assistance Report | Technical Assistance Reports | Apr 2020 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Consultants for PHI: Mindanao Agro-Enterprise Development Project | Firm - Consulting | Closed | 09 Sep 2020 | 23 Sep 2020 |
Development of the Philippine Rice Industry Roadmap (PRIR) 2021-2035 | Firm - Consulting | Closed | 18 Mar 2021 | 07 Apr 2021 |
TRTA Coordination Support Specialist | Individual - Consulting | Closed | 24 Jul 2020 | 07 Aug 2020 |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Contractor Address | Executing Agency | Contract Description | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|---|---|
Project Preparatory | Technical Assistance 9971 | 31 Aug 2020 | FCG ANZDEC LIMITED, NZL(NEW ZEALAND) in association with Finnish Consulting Group Asia Pte. Ltd(SINGAPORE) | SUITE 1,LEVEL 1,123 BROADWAY,P.O.BOX 99 RKET,AUCKLAND, NEW ZEALAND/ 99 Franklin Freemans Bay, Auckland,1011,New Zealand | Asian Development Bank | 2,300,000.00 | — | |
Project Preparatory | Technical Assistance 9971 | 10 Nov 2020 | NIRAS Finland Oy(FINLAND) in association with NIRAS Asia Manila Inc.(PHILIPPINES) | Varitehtaankatu 8 Vantaa, 01300 Finland | Asian Development Bank | 893,000.00 | — | |
Project Preparatory | Technical Assistance 9971 | 20 Jan 2021 | NAREE International Limited (HONGKONG, CHINA) in association with Inno-Change International Consultants, Inc. (PHILIPPINES) | Room A, 29/F, United Centre, 95 Queenswa Admiralty Hongkong, Hongkong, China | Asian Development Bank | 797,900.00 | — |
Procurement Plan
None currently available.