China, People's Republic of: Customized Low-Carbon Development Models in Rural and Small and Medium-Sized Towns

Sovereign Project | 54024-001

Project Details

  • Project Officer
    Sakai, Atsumasa
    East Asia Department
    Request for information
  • Country/Economy
    China, People's Republic of
  • Sector
    • Energy
Project Name Customized Low-Carbon Development Models in Rural and Small and Medium-Sized Towns
Project Number 54024-001
Country / Economy China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 6661-PRC: Customized Low-Carbon Development Models in Rural and Small and Medium-Sized Towns
Technical Assistance Special Fund US$ 238,000.00
Climate Change Fund US$ 750,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Knowledge solutions
Sector / Subsector

Energy / Energy efficiency and conservation - Renewable energy generation - solar - Renewable energy generation - wind

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

(i) Renewable energy interventions promoted (Strategic Planning for Rural Revitalization [2018 2022]),a and

(ii) Low-carbon modernized energy supply infrastructure in SMTs promoted (Strategy for the Revolution in Energy Production and Consumption).b

Project Outcome
Description of Outcome Readiness for investment in low-carbon energy supply infrastructure in rural areas and SMTs increased
Progress Toward Outcome
Implementation Progress
Description of Project Outputs

Research on optimal models with policy and guidelines for rural vitalization via low-carbon energy infrastructure in rural areas completed

Research on optimal models and needed policies for low-carbon energy infrastructure in SMTs completed

Status of Implementation Progress (Outputs, Activities, and Issues) The project was just approved on 8 December 2020. Consultants for the 2 components are already engaged. Research is ongoing.
Geographical Location Nation-wide
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design Stakeholders were consulted during project concept stage.
During Project Implementation Stakeholders are constantly being consulted during project implementation.
Responsible ADB Officer Sakai, Atsumasa
Responsible ADB Department East Asia Department
Responsible ADB Division EASI
Executing Agencies
National Energy Administration
38 Yuetan Nanjie, Beijing, 100824
Timetable
Concept Clearance 04 Sep 2020
Fact Finding 14 Oct 2020 to 16 Oct 2020
MRM -
Approval 08 Dec 2020
Last Review Mission -
Last PDS Update 27 Sep 2021

TA 6661-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
08 Dec 2020 30 Dec 2020 30 Dec 2020 31 Dec 2022 - -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
988,000.00 0.00 0.00 0.00 0.00 0.00 988,000.00 17 Jun 2022 160,863.07

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders


Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
KSTA Technical Assistance 6661 19 Jul 2021 Energy and Environmental Development Research Center | 2504, Building T2, Dazu Square, Rong Jing Dong Jie Beijing Economic-Technological Development Area, Beijing 100175 China National Energy Administration 235,597.00
Policy and Advisory Technical Assistance 6661 25 Jun 2021 TIANJIN UNIVERSITY | No. 92 Weijin Road, Nankai District, Tianjin, China 300072 National Energy Administration 269,900.00

Procurement Plan

None currently available.