fbpx 54026-007: Research on Comprehensive Management Planning Policy of Huangshui Basin in Qinghai Province | Asian Development Bank

China, People's Republic of: Research on Comprehensive Management Planning Policy of Huangshui Basin in Qinghai Province

Sovereign (Public) Project | 54026-007 Status: Active
 
Project Name Research on Comprehensive Management Planning Policy of Huangshui Basin in Qinghai Province
Project Number 54026-007
Country China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 6616-PRC: Research on Comprehensive Management Planning Policy of Huangshui Basin in Qinghai Province
Technical Assistance Special Fund US$ 258,000.00
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Knowledge solutions
Partnerships
Private sector development
Sector / Subsector

Agriculture, natural resources and rural development / Rural water policy, institutional and capacity development - Water-based natural resources management

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact Resilient ecological protection and security in the Yellow River basin achieved
Project Outcome
Description of Outcome Comprehensive management, planning, and policy for high-quality green development opportunities in the Yellow River basin improved
Progress Toward Outcome
Implementation Progress
Description of Project Outputs Analysis of current national, provincial, and municipal institutional, policy, and governance situation in the Huangshui River basin prepared
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nation-wide
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Fan, Mingyuan
Responsible ADB Department East Asia Department
Responsible ADB Division Environment, Natural Resources & Agriculture Division, EARD
Executing Agencies
Qinghai Provincial Finance Department
30 Huanghe Road, Xining, Qinghai
Timetable
Concept Clearance -
Fact Finding 13 Oct 2020 to 13 Oct 2020
MRM -
Approval 26 Nov 2020
Last Review Mission -
Last PDS Update 26 Nov 2020

TA 6616-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
26 Nov 2020 24 Dec 2020 24 Dec 2020 31 Dec 2022 - -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
258,000.00 0.00 0.00 0.00 0.00 0.00 258,000.00 26 Nov 2020 0.00

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Research on Comprehensive Management Planning Policy of Huangshui Basin in Qinghai Province Firm - Consulting Closed 07 Jan 2021 28 Jan 2021

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Policy and Advisory Technical Assistance 6616 29 Apr 2021 CHINA URBAN CONSTRUCTION DESIGN & RESEARCH INST. (CHINA,PEOPLE'SREP.OF) NO. 36 DESHENGMENWAI STREET, XICHENG DIS BEIJING PEOPLE'S REPUBLIC OF CHINA Qinghai Provincial Finance Department 208,400.00

Procurement Plan