China, People's Republic of : Building Climate Resilience through Adaptation Planning in the Yellow River Basin

Sovereign Project | 54026-014

The knowledge and support technical assistance (TA) cluster was approved on 28 October 2020 for $1.93 million financed on a grant basis by the Asian Development Bank's (ADB) Technical Assistance Special Fund (TASFother sources). On 8 July 2021, an increase in TA cluster amount for $.90 million also from TASF-other sources was approved, bringing the total TA amount to $2.83 million. There are 10 active subprojects under the TA. As part of the strategic framework approach to support ecological protection and high-quality development in the Yellow River basin, a minor change in the scope of the TA cluster and an increase in TA cluster amount are proposed to support the preparation of three additional subprojects, including Subproject 13. The Environment, Natural Resources, and Agriculture Division of ADB's East Asia Department administers and coordinates the implementation of the TA cluster.

Project Details

  • Project Officer
    Cardascia, Silvia
    Sectors Group
    Request for information
  • Country/Economy
    China, People's Republic of
  • Sector
    • Agriculture, natural resources and rural development

Related Projects

Project Name Building Climate Resilience through Adaptation Planning in the Yellow River Basin
Project Number 54026-014
Country / Economy China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 6948-PRC: Building Climate Resilience through Adaptation Planning in the Yellow River Basin
Technical Assistance Special Fund US$ 300,000.00
Climate Change Fund US$ 150,000.00
Operational Priorities OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
OP5: Promoting rural development and food security
Sector / Subsector

Agriculture, natural resources and rural development / Agricultural policy, institutional and capacity development - Rural water policy, institutional and capacity development - Water-based natural resources management

Gender Effective gender mainstreaming
Description The knowledge and support technical assistance (TA) cluster was approved on 28 October 2020 for $1.93 million financed on a grant basis by the Asian Development Bank's (ADB) Technical Assistance Special Fund (TASFother sources). On 8 July 2021, an increase in TA cluster amount for $.90 million also from TASF-other sources was approved, bringing the total TA amount to $2.83 million. There are 10 active subprojects under the TA. As part of the strategic framework approach to support ecological protection and high-quality development in the Yellow River basin, a minor change in the scope of the TA cluster and an increase in TA cluster amount are proposed to support the preparation of three additional subprojects, including Subproject 13. The Environment, Natural Resources, and Agriculture Division of ADB's East Asia Department administers and coordinates the implementation of the TA cluster. The National Development and Reform Commission, the leading agency for strategic development in the People's Republic of China (PRC), is the executing agency for the TA cluster, and strongly supports high-quality development in the Yellow River basin.
Project Rationale and Linkage to Country/Regional Strategy 2.The TA cluster is part of ADB's Yellow River Ecological Corridor (YREC) initiative, which promotes a multisector and integrated approach for lending operations and nonlending services, including TA, policy dialogue, and knowledge sharing activities. The YREC program was shaped by ADB's experience from the Yangtze River Economic Belt initiative and aligns with the goals of the Outline of Ecological Protection and High-Quality Development Plan of the Yellow River. The TA cluster comprises a series of subprojects, each focused on different aspects of river basin management, to help achieve the aims of the YREC program in its six thematic areas of intervention.
Impact

Resilient ecological protection and security in the Yellow River basin achieved

Project Outcome
Description of Outcome

Adaptation planning and resilience in the Yellow River basin improved

Progress Toward Outcome
Implementation Progress
Description of Project Outputs

Climate risk assessment and recommendations on adaptation measures in the Yellow River basin finalized

YRBAP aligned with the PRC's NSCA 2035 produced

Knowledge and capacity on adaptation planning and resilience in the basin enhanced

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nation-wide
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Cardascia, Silvia
Responsible ADB Department Sectors Group
Responsible ADB Division Agriculture, Food, Nature, and Rural Development Sector Office (SG-AFNR)
Executing Agencies
Department of International Cooperation
Timetable
Concept Clearance -
Fact Finding 14 Mar 2022 to 18 Mar 2022
MRM -
Approval 21 Aug 2022
Last Review Mission -
Last PDS Update 21 Aug 2022

TA 6948-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
21 Aug 2022 12 Sep 2022 12 Sep 2022 30 Jun 2025 - -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
450,000.00 0.00 0.00 0.00 0.00 0.00 450,000.00 09 Sep 2023 102,257.44

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Firm Firm - Consulting Closed

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Capacity Development Technical Assistance Technical Assistance 6948 10 Jan 2023 National Center of Climate Change Strategy and International Cooperation (P.R.C.) | No.5 Houyingfang Hutong, Xicheng District, Beijing, China Department of International Cooperation 417,000.00

Procurement Plan

None currently available.