Tonga : COVID-19 Emergency Response

Sovereign Project | 54135-002

Project Name COVID-19 Emergency Response
Project Number 54135-002
Country / Economy Tonga
Project Status Closed
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0693-TON: COVID-19 Emergency Response (Additional Financing)
Asia Pacific Disaster Response Fund US$ 470,000.00
Operational Priorities OP1: Addressing remaining poverty and reducing inequalities
Sector / Subsector

Health / Disease control of communicable disease

Gender No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Tonga's immediate financial, logistic, and other constraints needs during disease outbreak preparedness and emergency response alleviated

Project Outcome
Description of Outcome

N/A

Progress Toward Outcome
Implementation Progress
Description of Project Outputs

N/A

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Nation-wide
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Lam, Ki Fung Kelvin
Responsible ADB Department Pacific Department
Responsible ADB Division PASP
Executing Agencies
Ministry of Finance
Timetable
Concept Clearance -
Fact Finding 31 Mar 2020 to 31 Mar 2020
MRM 13 May 2020
Approval 06 Apr 2020
Last Review Mission -
Last PDS Update 23 Apr 2020

Grant 0693-TON

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
06 Apr 2020 08 Apr 2020 09 Apr 2020 08 Oct 2020 - 03 Jun 2021
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 0.47 Cumulative Contract Awards
ADB 0.47 17 Jun 2022 0.47 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 17 Jun 2022 0.47 0.00 100%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.