Thailand : COVID-19 Active Response and Expenditure Support Program
Project Details
-
Project Officer
Hattel, Kelly L.
Southeast Asia Department
Request for information -
Country/Economy
Thailand -
Sector
- Public sector management
Project Name | COVID-19 Active Response and Expenditure Support Program | ||||||||||||
Project Number | 54177-001 | ||||||||||||
Country / Economy | Thailand |
||||||||||||
Project Status | Closed | ||||||||||||
Project Type / Modality of Assistance | Loan |
||||||||||||
Source of Funding / Amount |
|
||||||||||||
Operational Priorities | OP1: Addressing remaining poverty and reducing inequalities OP2: Accelerating progress in gender equality OP6: Strengthening governance and institutional capacity OP7: Fostering regional cooperation and integration |
||||||||||||
Sector / Subsector |
Health / Disease control of communicable disease - Health system development Public sector management / Public expenditure and fiscal management - Social protection initiatives |
||||||||||||
Gender | Effective gender mainstreaming | ||||||||||||
Description | |||||||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||||||
Impact | Adverse impact of COVID-19 on the economic growth and poverty mitigated |
Project Outcome | |
---|---|
Description of Outcome | Healthcare system's preparedness for future pandemic surges improved and adverse social and economic impacts of COVID-19 minimized |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Measures to prepare the healthcare system for pandemic surges implemented Support to the poor and the vulnerable impacted by COVID-19 expanded Measures to support businesses, including SMEs impacted by COVID-19, implementedg |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nation-wide |
Safeguard Categories | |
---|---|
Environment | C |
Involuntary Resettlement | C |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Hattel, Kelly L. |
Responsible ADB Department | Southeast Asia Department |
Responsible ADB Division | Public Management, Financial Sector and Trade Division, SERD |
Executing Agencies |
Ministry of Finance |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | 08 Apr 2020 to 25 May 2020 |
MRM | 03 Jun 2020 |
Approval | 26 Jun 2020 |
Last Review Mission | - |
Last PDS Update | 01 Jul 2020 |
Loan 3945-THA
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
26 Jun 2020 | 16 Nov 2020 | 05 Jan 2021 | 30 Jun 2021 | 31 Dec 2021 | 31 Jan 2022 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 500.00 | Cumulative Contract Awards | |||
ADB | 500.00 | 17 Jun 2022 | 500.00 | 0.00 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Jun 2022 | 500.00 | 0.00 | 100% |
Loan 3949-THA
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
26 Jun 2020 | 16 Nov 2020 | 05 Jan 2021 | 30 Jun 2021 | 31 Dec 2021 | 31 Jan 2022 |
Financing Plan | Loan Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 1,000.00 | Cumulative Contract Awards | |||
ADB | 1,000.00 | 17 Jun 2022 | 1,000.00 | 0.00 | 100% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 17 Jun 2022 | 1,000.00 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
Title | Document Type | Document Date |
---|---|---|
Thailand: COVID-19 Active Response and Expenditure Support Program | Brochures and Flyers | Jun 2023 |
แผนงาน COVID-19 Active Response and Expenditure Support Program (CARES) ของประเทศไทย | Brochures and Flyers | Jun 2023 |
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.