China, People's Republic of: Research on Addressing Climate Change in Ningxia through the Use of Science and Technology

Sovereign Project | 55033-001

Project Details

  • Project Officer
    Ramamurthy, Arun
    East Asia Department
    Request for information
  • Approval Date
    28 September 2021
  • Country
    China, People's Republic of
  • Sector
    • Energy
Project Name Research on Addressing Climate Change in Ningxia through the Use of Science and Technology
Project Number 55033-001
Country China, People's Republic of
Project Status Approved
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 6783-PRC: Research on Addressing Climate Change in Ningxia through the Use of Science and Technology
Technical Assistance Special Fund US$ 300,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Knowledge solutions
Sector / Subsector

Agriculture, natural resources and rural development / Water-based natural resources management

Energy / Energy sector development and institutional reform

Industry and trade / Large and medium industries

Information and communication technology / ICT industries and ICT-enabled services

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact Effective climate change-related planning and management in Ningxia achieved
Project Outcome
Description of Outcome Knowledge and capacity on innovative solutions for climate change mitigation and adaptation in Ningxia applied
Progress Toward Outcome
Implementation Progress
Description of Project Outputs

Research on technological innovations to improve climate mitigation and resilience in Ningxia produced

Climate change measurement indicators for the identified key industries in Ningxia developed

Knowledge on Ningxia's approach to manage climate change effects enhanced

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Ningxia Hui Autonomous Region
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services A consulting firm and national consultants will be engaged during the implementation of the TA.
Procurement The following will be procured by consultants: software, hardware, and computing equipment.
Responsible ADB Officer Ramamurthy, Arun
Responsible ADB Department East Asia Department
Responsible ADB Division EASI
Executing Agencies
Ningxia Finance Department
416 Jiefangxijie, Xingging District,
Yinchuan, Ningxia China, 7500001
Science and Technology Department of Ningxia
No. 95 Xiqiaoxiang, Jiefangxi Street,Xingqing District,Yinchuang Municipality, Ningxia, PRC 750001
Timetable
Concept Clearance 22 Jul 2021
Fact Finding 02 Aug 2021 to 02 Aug 2021
MRM -
Approval 28 Sep 2021
Last Review Mission -
Last PDS Update 28 Sep 2021

TA 6783-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
28 Sep 2021 - - 31 Jul 2024 - -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
300,000.00 0.00 0.00 0.00 0.00 0.00 300,000.00 28 Sep 2021 0.00

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.


Contracts Awarded

No contracts awarded for this project were found


Procurement Plan

None currently available.