Maldives : Supporting COVID-19 Response and Vaccination Program
To address the challenges affecting the Maldives' health system in mitigating the COVID-19 pandemic, the transaction TA will support (i) the government to rapidly strengthen its health system resilience and capacity, and (ii) developing long-term COVID-19 pandemic response and vaccination plans for expanded coverage in the upcoming years. The TA will further support the preparation of the ensuing COVID-19 vaccine financing project under APVAX
Project Details
-
Project Officer
Chen, Dai-Ling
Sectors Group
Request for information -
Country/Economy
Maldives -
Sector
- Health
Project Name | Supporting COVID-19 Response and Vaccination Program | ||||
Project Number | 55086-002 | ||||
Country / Economy | Maldives |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Operational Priorities | OP1: Addressing remaining poverty and reducing inequalities OP7: Fostering regional cooperation and integration |
||||
Sector / Subsector | Health / Disease control of communicable disease |
||||
Gender | No gender elements | ||||
Description | To address the challenges affecting the Maldives' health system in mitigating the COVID-19 pandemic, the transaction TA will support (i) the government to rapidly strengthen its health system resilience and capacity, and (ii) developing long-term COVID-19 pandemic response and vaccination plans for expanded coverage in the upcoming years. The TA will further support the preparation of the ensuing COVID-19 vaccine financing project under APVAX | ||||
Project Rationale and Linkage to Country/Regional Strategy | The third wave of the COVID-19 pandemic revealed the vulnerabilities in the country's health system capacity that require an urgent need to improve the health systems in managing emergency medical services (EMS), strengthen coordination between health facilities, and improve the capacity to respond to COVID-19 and future pandemics. Consultations with the Ministry of Health (MOH) expressed that the vulnerabilities to be addressed immediately are due to (i) inefficient EMS for COVID-19 patients; (ii) unintegrated health information system (HIS) across health facilities, which is needed for effective COVID-19 patient information sharing during case referrals; (iii) unavailability of tracking and identifying COVID-19 variants; (iv) inadequate mental health support for COVID-19 survivors and frontline health professionals involved in COVID-19 response; and (v) lack of long-term planning for the COVID-19 pandemic response and vaccination. | ||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nation-wide |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Business Opportunities | |
---|---|
Consulting Services | Firm (QCBS): 18 person-months (International) and 11 person months (National) Individual (ICS): 10 person-months (International) and 54 person-months (National) |
Procurement | Contracts may be procured under consultant contracts and may use competitive or direct contracting procurement method as appropriate |
Responsible ADB Officer | Chen, Dai-Ling |
Responsible ADB Department | Sectors Group |
Responsible ADB Division | Human and Social Development Sector Office (SG-HSD) |
Executing Agencies |
Ministry of Finance (formerly Ministry of Finance and Treasury) |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | - |
Approval | 10 Nov 2021 |
Last Review Mission | - |
Last PDS Update | 12 Dec 2022 |
TA 6820-MLD
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
10 Nov 2021 | 02 Dec 2021 | 02 Dec 2021 | 30 Nov 2023 | 31 May 2025 | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
0.00 | 2,000,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 2,000,000.00 | 09 Sep 2023 | 619,859.14 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Supporting COVID-19 Response and Vaccination Program: Technical Assistance Report | Technical Assistance Reports | Nov 2021 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
TA and Project Implementation Coordinator 2 | Individual - Consulting | Closed | ||
Emergency Medical Service Information System Consulting Firm | Firm - Consulting | Closed | ||
Senior Public Health Specialist | Individual - Consulting | Closed | ||
Costing and Fiduciary Expert | Individual - Consulting | Closed | ||
Social Safeguards Expert | Individual - Consulting | Closed | ||
Environmental Safeguards Expert | Individual - Consulting | Closed | ||
Vaccine Cold Chain and Logistic Expert | Individual - Consulting | Closed | ||
Procurement Expert | Individual - Consulting | Closed | ||
TA and Project Implementation Coordinator 1 | Individual - Consulting | Closed |
Contracts Awarded
Contract Title | Approval Number | Contract Date | Contractor | Address | Executing Agency | Total Contract Amount (US$) | Contract Amount Financed by ADB (US$) |
---|---|---|---|---|---|---|
Project Preparatory Technical Assistance | Technical Assistance 6820 | 01 Sep 2022 | IQVIA Consulting and Information Services India Private Limited (INDIA) in association with Ziqitza Healthcare Limited (INDIA) | Unit no 1031, 10th Floor, Hindustan times Building, K.G Marg, Connaught Place, New Delhi, 110001 India | Ministry of Finance | 619,720.00 | — |
Procurement Plan
None currently available.