China, People's Republic of : Preparing Low-Carbon Development Projects

Sovereign Project | 56204-001

Project Details

  • Project Officer
    Zhang, Lei
    Sectors Group
    Request for information
  • Country/Economy
    China, People's Republic of
  • Sector
    • Energy
Project Name Preparing Low-Carbon Development Projects
Project Number 56204-001
Country / Economy China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 6986-PRC: Preparing Low-Carbon Development Projects
Technical Assistance Special Fund US$ 1.20 million
TA 6986-PRC: Preparing Low-Carbon Development Projects (Supplementary)
Technical Assistance Special Fund US$ 400,000.00
Operational Priorities OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
OP4: Making cities more livable
OP6: Strengthening governance and institutional capacity
Sector / Subsector

Energy / Energy efficiency and conservation

Transport / Urban public transport - Urban roads and traffic management

Water and other urban infrastructure and services / Urban housing - Urban sewerage - Urban solid waste management

Gender Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Chongqing, Ningbo, Shaanxi
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design The proposed TA was identified, conceptualized, and prepared through discussions and consultations with project officers of the ensuing projects.
During Project Implementation During project implementation, the TA will be jointly monitored by the project officer assigned to the TA and the project officers of each ensuing project within the SG-ENE and SG-URB. The TA is supporting the preparatory works and due diligence of three projects (i) Ningbo Green and Low-Carbon Development Project, (ii) Shaanxi Low-Carbon and Integrated Urban-Rural Sustainable Development Program, and (iii) Chongqing Nature-Based, Green, Low-Carbon, and High-Quality Urban Development Demonstration, which are all for 2024 pipeline. The concept papers of Ningbo and Shaanxi low-carbon projects were approved on 11 July 2023 and 18 September 2023, respectively.
Business Opportunities
Consulting Services TA activities for each ensuing project will require a team of international and national consultants to be engaged by ADB. Recruitments based on the requirements of each ensuing project will be done in accordance with ADB's Procurement Policy (2017, as amended from time to time) and associated Staff Instructions.
Procurement ADB will carry out procurement following the ADB Procurement Policy (2017, as amended from time to time) and its associated project administration instructions/and or staff instructions.
Responsible ADB Officer Zhang, Lei
Responsible ADB Department Sectors Group
Responsible ADB Division Energy Sector Office (SG-ENE)
Executing Agencies
Chongqing Municipal Government
Ningbo Municipal Government
SHAANXI PROVINCIAL GOVERNMENT
Timetable
Concept Clearance -
Fact Finding -
MRM -
Approval 04 Nov 2022
Last Review Mission -
Last PDS Update 25 Sep 2023

TA 6986-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
04 Nov 2022 30 Nov 2022 30 Nov 2022 31 Dec 2026 - -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
1,600,000.00 0.00 0.00 0.00 0.00 0.00 1,600,000.00 02 Apr 2024 599,221.59

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Preparing Low-Carbon Development Projects: Technical Assistance Report Technical Assistance Reports Nov 2022

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
Results-based Lending Specialist Individual - Consulting Closed
Preparing Chongqing Nature-Based, Green, Low-Carbon, and High-Quality Urban Development Demonstration Firm - Consulting Closed
Shaanxi Low-Carbon and Integrated Urban-Rural Sustainable Development Program-Consulting Firm Firm - Consulting Closed
National Results-Based Lending Program Development Specialist-Shaanxi Project Individual - Consulting Closed
National Cooling Specialist Individual - Consulting Closed
International Cooling Specialist Individual - Consulting Closed
International Energy Efficiency Specialist/team leader Individual - Consulting Closed
National Poverty, Social Development, and Gender Specialist Individual - Consulting Closed
National Financial Management and Institutional Specialist Individual - Consulting Closed
National Energy Specialist/Deputy Team Leader Individual - Consulting Closed
National Resettlement Specialist Individual - Consulting Closed
National Coordinator Individual - Consulting Closed
National Environment Specialist Individual - Consulting Closed
National Industry System, Gas Turbine and Cogeneration Specialist Individual - Consulting Closed
International Economist Individual - Consulting Closed
International Industry System, Gas Turbine and Cogeneration Specialist Individual - Consulting Closed
International Climate Change Specialist Individual - Consulting Closed
International Carbon Capture, Usage and Storage and Industry Heat Cascade Use Specialist Individual - Consulting Closed

Contracts Awarded

Contract Title Approval Number Contract Date Contractor | Address Executing Agency Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Project Preparatory Technical Assistance Technical Assistance 6986 24 Jan 2024 NAREE International Limited (HK, CHINA) in association with Urbanlogic Limited (HK, CHINA) | Room A, 29/F, United Centre, 95 Queensway, Admiralty, Hong Kong, China Shaanxi Provincial Government 348,720.00
Project Preparatory Technical Assistance Technical Assistance 6986 09 Oct 2023 NAREE International Limited (HK, CHINA) in association with Urbanlogic Ltd. (HK, CHINA) | Room A, 29/F, United Centre, 95 Queensway, Admiralty Hong Kong, China Shaanxi Provincial Government 321,987.00

Procurement Plan