Bangladesh : Power Transmission Strengthening and Integration of Renewable Energy Project

Sovereign Project | 57232-001

The proposed Power Transmission Strengthening and Integration of Renewable Energy Project (the project) will support the government in (i) enhancing the reliability, resiliency, and efficiency of the power transmission grid in the rural areas and (ii) integrating the anticipated increase in renewable energy generation in the Variable Renewable Energy (VRE) Hub in Southern Chattogram in Bangladesh. The project will have the following outcome: quality, reliability, and efficiency of power supply system in the project area improved. The project outputs will be (i) Disaster- and Climate-resilient and GESI-responsive power transmission infrastructure enhanced and modernized, (ii) Integration of renewable energy supported, and (iii) Institutional capacity of PGCB improved. The executing agency is Power Grid Company of Bangladesh (PGCB). The project will be financed by a loan of $200 million from Asian Development Bank's (ADB) ordinary capital resources. The project outputs as follows:

Project Details

Project Name
Power Transmission Strengthening and Integration of Renewable Energy Project
Project Number
57232-001
Country / Economy
  • Bangladesh
Project Status
Proposed
Project Type / Modality of Assistance
  • Loan
Source of Funding / Amount
Loan: Power Transmission System Expansion and Improvement Project
Source Amount
Ordinary capital resources US$ 200.00 million
Operational Priorities
  • OP2: Accelerating progress in gender equality
  • OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
  • OP5: Promoting rural development and food security
  • OP6: Strengthening governance and institutional capacity
Sector / Subsector
  • Energy / Electricity transmission and distribution

Gender
Effective gender mainstreaming
Description

The proposed Power Transmission Strengthening and Integration of Renewable Energy Project (the project) will support the government in (i) enhancing the reliability, resiliency, and efficiency of the power transmission grid in the rural areas and (ii) integrating the anticipated increase in renewable energy generation in the Variable Renewable Energy (VRE) Hub in Southern Chattogram in Bangladesh. The project will have the following outcome: quality, reliability, and efficiency of power supply system in the project area improved. The project outputs will be (i) Disaster- and Climate-resilient and GESI-responsive power transmission infrastructure enhanced and modernized, (ii) Integration of renewable energy supported, and (iii) Institutional capacity of PGCB improved. The executing agency is Power Grid Company of Bangladesh (PGCB). The project will be financed by a loan of $200 million from Asian Development Bank's (ADB) ordinary capital resources. The project outputs as follows:

Output 1: Disaster- and climate-resilient and GESI-responsive power transmission infrastructure enhanced and modernized. This output will support building disaster- and climate-resilient and GESI-responsive power transmission infrastructure through (i) construction of 1,980 megavolt-ampere (MVA) of 230/132 kilovolt (KV) and 1,230 MVA of 132/33 kV transformers installed in 9 substations at Monohordi, Dupchachia, Tungipara, Kustia, Mathbaria, Paikgacha, Matlab, Madhavpur, and Chatkhil, (ii) installing 6.7 kilometer (km) (230kV double circuit) and 141.3 km (132 kV double circuit) of new disaster- and climate-resilient transmission lines, and 75 km (132kV double circuit) of reconducting transmission lines, and (iii) installing 10 numbers of 132kV bay extensions.

Output 2: Integration of renewable energy supported. This output will facilitate the integration of renewable energy generation from the VRE Hub in Southern Chattogram and enhance the reliability, resilience, and efficiency of the national power grid by (i) installing 2,160 MVA of 400/230/132 kV transformer capacities in a new disaster- and climate-resilient and GESI-responsive substation, (ii) installing 6.7 km of 400 kV double circuit, 0.5 km of 230kV double circuit, and 1.3 km of 132kV double circuit new disaster- and climate-resilient transmission lines.

Output 3: Institutional capacity of PGCB improved. This output will strengthen the capacity of PGCB by (i) increasing PGCB staff's (90% of relevant women staff) knowledge and capacity of advanced technologies, operation and maintenance skills, and emergency management of the power transmission system, and environmental and social safeguards, (ii) strengthening the in-house corporate environmental, gender and social unit, including in respect of corporate environmental and social safeguard procedures, (iii) developing a corporate GESI strategy, (iv) developing a roadmap and action plan for commercial borrowing for PGCB, and identifying areas where the capacity of PGCB can be improved, and (v) enhancing capacity for PGCB's fixed asset registry management.

The project scope include five works (EPC) as follows:

(i)Design, Supply and Installation of 400/230/132 kV AIS Substation at Pekua and associated single /double circuit 400kv/220kv/132kv LILO Lines on turnkey basis on turnkey basis - 1 Lot: $ 66.53 M

(ii)Design, Supply and Installation of (a) 230/132 /33 kV AIS Substations at Madhabpur and Monohardi, (b) 2x 132 kv bay extension at Bajitpur Substation, and (c) and associated transmission infrastructure on turnkey basis -1 Lot: $ 45.03 M

(iii) Design, Supply, Installation and commissioning of 132/33KV AIS at 3 locations and 2x132 kV AIS Bay Extension at 3 locations on Turnkey basis - 1Lot: $ 22.14 M

(iv)Design, Supply, Installation and commissioning of 132/33KV AIS at 4 locations and 2x132 kV AIS Bay Extension at Kachua 230/132/33 kV Substation- 1 Lot: $26.26 M

(v)Design, Supply, Installation and commissioning of (a) 132kV double circuit lines (Single ACSR Grosbeak) between Gopalganj-Tungipara, Satkhira-Paikgacha, Kachua- Matlab(N), Bhandaria-Mathbaria and (b) LILO of Chowmuhani-Ramganj, Shahjibazar Brahmanbaria, Bogura(S)-Naogaon and Bheramara Rajbari 132kV single / double circuit lines and (c) Stringing of ACCC Grosbeak Conductor in Shahjibazar-Brahmanbaria-Ashuganj 132kV line - 1Lot: $ 33.21 M.

Project Rationale and Linkage to Country/Regional Strategy
The objective of this project is to enhance the reliability, resiliency, and efficiency of electricity supply to meet the growing demand in rural areas and to promote the integration of renewable energy in the southern chattogram area in Bangladesh. The project will support enhancement of transmission network infrastructures including installation and augmentation of substations and transmission lines, implementing advanced technologies, and optimizing maintenance practices and solutions.
Impact
(i)Uninterrupted power supply for rural areas of Bangladesh achieved. (Eighth Five-Year Plan of Bangladesh, July 2020
Outcome

Reliability and efficiency of electricity supply in the project area improved.

Outputs

Climate resilient power transmission infrastructure are established in rural areas.

Integration of Renewable Energy is supported.

Institutional capacity of PGCB is improved.

Geographical Location
Nation-wide

Safeguard Categories

Environment
B
Involuntary Resettlement
B
Indigenous Peoples
C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Contact

Responsible ADB Officer
Jung, Choon Sik
Responsible ADB Department
Sectors Group
Responsible ADB Division
Energy Sector Office (SG-ENE)
Executing Agencies
Power Grid Company of Bangladesh, Ltd. (PGCB)

Timetable

Concept Clearance
11 Dec 2023
Fact Finding
20 May 2024 to 29 May 2024
MRM
-
Approval
-
Last Review Mission
-
Last PDS Update
11 Dec 2023

Funding

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

None currently available.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Power Transmission Strengthening and Integration of Renewable Energy Project: Resettlement Plan Resettlement Plans Sep 2024

Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

Tender Title Type Status Posting Date Deadline
57232-001 (BAN) - Power Transmission Strengthening and Integration of Renewable Energy Project Invitation for Bids Closed

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.