The project will include a natural gas fired power plant (CCPP) and a liquefied natural gas (LNG) terminal. The LNG terminal, located near Kutubdia Island, consists of a mooring point, jetty and pipeline infrastructure to connect an off-shore FSRU to the mainland. The 718 MW CCPP, utilizing re-gasified LNG (RLNG) as fuel, is proposed to be located on land allotted by Bangladesh Power Development Board (BPDB), in Meghnaghat, Narayanganj District.

The report and recommendation of the President to the Board of Directors (RRP) document describes the terms and conditions of a project for consideration and approval by ADB's Board of Directors. This document dated November 2017 is provided for the ADB project 50253-001 in Bangladesh.

Linked Documents

  1. Sector Overview [Withheld from Disclosure per Para. 97 (v) of PCP 2011]
  2. Client Information [Withheld from Disclosure per Para. 97 (v) of PCP 2011]
  3. Details of Implementation Arrangements [Withheld from Disclosure per Para. 97 (v) of PCP 2011]
  4. Contribution to the ADB Results Framework
  5. Financial Analysis [Withheld from Disclosure per Para. 97 (v) of PCP 2011]
  6. Economic Analysis [Withheld from Disclosure per Para. 97 (v) of PCP 2011]
  7. Country Economic Indicators
  8. Summary Poverty Reduction and Social Strategy [Withheld from Disclosure per Para. 97 (v) of PCP 2011]
  9. Safeguards and Social Dimensions Summary [Withheld from Disclosure per Para. 97 (v) of PCP 2011]
  10. Environmental and Social Impact Assessment: Reliance Bangladesh LNG and Power Limited
  11. Environmental and Social Impact Assessment: Reliance Bangladesh LNG Terminal Limited
  12. Resettlement Framework
  13. Integrity and Tax Due Diligence [Withheld from Disclosure per Para. 97 (v) of PCP 2011]