Documents Produced Under Grant/Loans/TA | September 2017

This Stakeholder Engagement Plan (SEP) describes Baikonur Solar LLP's approach to interacting with stakeholders, including the general public, and the disclosure of relevant information with respect to the company’s current operations and the construction of the 50MW Solar photovoltaic power plant. The SEP includes a strategy to provide timely, meaningful and appropriate information to stakeholders and ensure the opportunity for such stakeholders to express their views and comments. The SEP provides a mechanism for the consideration and response to comments and potential grievances raised by stakeholders.

Documents produced under projects are material produced in the course of the project, or as outputs.

This document dated September 2017 is provided for the ADB project 51250-001 in Kazakhstan.