West Kalimantan Power Grid Strengthening Project: Report and Recommendation of the President
Reports and Recommendations of the President
|
August 2013
SHARE THIS PAGE
Reports and recommendations of the president (RRP) describes the terms and conditions of a project for consideration for approval by ADB.
This document dated August 2013 is provided for the ADB project 41074-013 in Indonesia.
Linked Documents
- Loan Agreement
- Grant Agreement
- Project Agreement
- Sector Assessment (Summary): Energy
- Project Administration Manual
- Contribution to the ADB Results Framework
- Development Coordination
- Financial Analysis
- Economic Analysis
- Country Economic Indicators
- Summary Poverty Reduction and Social Strategy
- Initial Environmental Examination
- Resettlement Plan: Combined Resettlement Customary Communities Development Plan (275 kV)
- Resettlement Plan: Combined Resettlement, Ethnic Minority and Development Plan (150 kV)
- Risk Assessment and Risk Management Plan
- Financial Performance and Projection for PT (Persero) Perusahaan Listrik Negara (available on request)
- Increasing Access to Electricity for the Poor
- Climate Change and Carbon Credits
- INO RRP: Java–Bali Electricity Distribution Performance Improvement Project
- West Kalimantan Power Sector Analysis (available on request)