Nepal : Kali Gandaki "A" Hydroelectric Project

Kali Gandaki "A" Hydroelectric Project Project | LN1452

Project Details

Project Name Kali Gandaki "A" Hydroelectric Project
Project Number 26362
Country / Economy Nepal
Project Status Closed
Project Type / Modality of Assistance Loan
Sector / Subsector Energy - Large Hydropower
Funding
Loan 1452-: Kali Gandaki "A" Hydroelectric Project
Asian Development Fund US$ 152.26 million
Approval 23 Jul 1996

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Kali Gandaki "A" Hydroelectric Project Project/Program Completion Reports Apr 2004
Kali Gandaki "A" Hydroelectric Power Project Reports and Recommendations of the President Jun 1996

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Kali Gandaki "A" Hydroelectric Power Project Summary Environmental Impact Assessments Mar 1996

Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Nepal: Kali Gandaki “A” Hydroelectric Project Project Performance Evaluation Reports Dec 2012

Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.