Georgia: Adjaristsqali Hydropower Project

SHARE THIS PAGE

Issues

  • Impacts of the project on the natural and social environment of the village
  • Village safety

Status

  • Complaint received, 8 March 2018
  • Complaint acknowledged and registered, 8 March 2018
  • Eligibility (eligible), 12 March 2018
  • Closed, 7 December 2020
    • European Bank for Reconstruction and Development Independent Project Accountability Mechanism Problem Solving Completion Report, October 2020
    • International Finance Corporation and Multilateral Investment Guarantee Agency Compliance Advisor Ombudsman Dispute Resolution Conclusion Report, October 2020

Details