  • Alignment of transmission line going through houses and land
  • Health issues

Status

  • Complaint received, 5 October 2017
  • Complaint acknowledged and registered, 6 October 2017
  • Eligibility (not eligible, complainants have yet to address problem with concerned ADB operations department), 9 October 2017
  • Closed, 30 March 2021

Details

  • Date Recieved / Request ID
    05 Oct 2017 / SPF-2017-11-02-0068
  • Project Number N/A
  • Country/Economy
    Sri Lanka